3460 S CENTINELA AVE 90066
Certificate Information: 3460 S CENTINELA AVE 90066
- Application / Permit
- 24020-20000-00101
- Plan Check / Job No.
- B24VN00680
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) 6' HIGH MAX X 112'-4.5" IN LENGTH RETAINING WALL ON PILES.
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/5/2025
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | RAPHAEL ROSAS |
| Corrections Issued | 1/30/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 1/30/2024 | STEVEN KIM |
| Building Plans Picked Up | 1/31/2024 | APPLICANT |
| Applicant returned to address corrections | 8/19/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/29/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 9/16/2024 | RAPHAEL ROSAS |
| Issued | 10/31/2024 | APPLICANT |
| Permit Finaled | 3/4/2025 | DANIEL VARNUM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/16/2024 | BRENDEN HAWK |
| "Q" conditions | Cleared | 7/23/2024 | DAVID URITA |
| "T" removal | Cleared | 7/23/2024 | DAVID URITA |
| Tract Map conditions | Cleared | 7/23/2024 | DAVID URITA |
| ZA Case | Cleared | 7/23/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | BRENDEN HAWK |
| Work Adjacent to Public Way | Cleared | 8/10/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 9/16/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Lavie'S Construction Inc; Lic. No.: 1012582-B | 640 S SAN VICENTE BLVD #254 LOS ANGELES, CA 90048 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
| Engineer | Esmaily-Radvar,, Shahrokh; Lic. No.: GE2742 | 5 HODGENVILLE IRVINE, CA 92620 |
Inspector Information
| DANIEL VARNUM, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/12/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Pre-Inspection | 11/15/2024 | Partial Inspection | DANIEL VARNUM |
| Piling/Pier/Caisson | 12/18/2024 | Corrections Issued | DANIEL VARNUM |
| Deputy Reinf. Concrete | 12/24/2024 | Conditional Approval | DANIEL VARNUM |
| Special/Order Compliance | 12/24/2024 | Corrections Issued | DANIEL VARNUM |
| Footing/Foundation/Slab | 1/16/2025 | Partial Inspection | DANIEL VARNUM |
| Reinforced Masonry Frame | 1/22/2025 | Approved | DANIEL VARNUM |
| Masonry Wall/Backfill | 2/4/2025 | Partial Approval | DANIEL VARNUM |
| Final | 3/4/2025 | Permit Finaled | DANIEL VARNUM |