5222 N EXCHANGE ST 90039
Certificate Information: 5222 N EXCHANGE ST 90039
- Application / Permit
- 24020-10000-02372
- Plan Check / Job No.
- B24LA37145
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- EPLAN Installation of aggregate bin, conveyor system and ancillary equipment to supply aggregates on demand to an existing ready mixed plant. The aggregate storage bin is an accessory piece of equipment serving the primary use of the site manufacturing ready mixed concrete.
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Issued on 8/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2024 | APPLICANT |
| Assigned to Zoning Architect | 1/2/2025 | MELISSA QUINONES |
| Assigned to Plan Check Engineer | 1/9/2025 | MICHAEL LOPEZ |
| Corrections Issued | 1/21/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 1/22/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 4/3/2025 | STARR CHEN |
| Plan Check Approved | 8/4/2025 | MICHAEL LOPEZ |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 1/17/2025 | Daniel San Juan |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kjelstrom,, Shaun; Lic. No.: NA76184 | , |
| Engineer | Mitchell,, Gregory; Lic. No.: GE2364 | 22885 E SAVI RANCH PKWY STE E YORBA LINDA, CA 92887 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2025 | Partial Inspection | LUIS CCAMACHO |
| Footing/Foundation/Slab | 12/29/2025 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 1/12/2026 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 1/28/2026 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 3/5/2026 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 3/13/2026 | Partial Approval | LUIS CCAMACHO |
| Footing/Foundation/Slab | 4/16/2026 | Partial Approval | LUIS CCAMACHO |