870 N NORMAN PL 90049
Certificate Information: 870 N NORMAN PL 90049
- Application / Permit
- 24020-10000-02163
- Plan Check / Job No.
- B24LA31281
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW DETACHED BUILT UP DECK ON PILES PER SOILS REPORT.
- Permit Issued
- Issued on 7/5/2025
- Issuing Office
- Current Status
- Issued on 7/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 11/25/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/26/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 3/14/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 6/24/2025 | SERGIO GUTIERREZ |
| Issued | 7/5/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/13/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 1/13/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 1/13/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 1/13/2025 | LIAM ODONOVAN |
| Certificate of Compliance | Cleared | 1/13/2025 | DANIEL CORONADO |
| Private street | Cleared | 1/13/2025 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 1/17/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 1/17/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 1/17/2025 | LIAM ODONOVAN |
| Watercourse | Cleared | 1/21/2025 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 6/3/2025 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 6/3/2025 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: NA53875 | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 10/20/2025 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/20/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/24/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 11/24/2025 | Partial Approval | DANIEL VERA |
| Deputy Reinf. Concrete | 11/25/2025 | Conditional Approval | ANDREW NAVE |
| Wood Frame | 3/24/2026 | Approved | EVAN COOPER |