556 W SEPULVEDA ST 90731
Certificate Information: 556 W SEPULVEDA ST 90731
- Application / Permit
- 24020-10000-02104
- Plan Check / Job No.
- B24LA32126
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (61) Open Parking Lot
- Work Description
- Use of land permit for New parking lot per ZA-2023-5144-CU operation and expansion of a public parking area associated with a church in the R2-1XL-CPIO zone.
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- Current Status
- Issued on 8/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Zoning Architect | 12/12/2024 | RONALD GREENE |
| Assigned to Plan Check Engineer | 12/19/2024 | JOE VO |
| Corrections Issued | 12/21/2024 | JOE VO |
| Quality Review Completed | 12/23/2024 | GARO TELMI |
| Plan Check Approved | 4/29/2025 | JOE VO |
| Issued | 8/19/2025 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/13/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 1/13/2025 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | XOCHITL ARQUIETA |
| Permit | Cleared | 1/14/2025 | XOCHITL ARQUIETA |
| DAS Clearance | Cleared | 2/19/2025 | Ricardo Ramirez Solis |
| Community Plan Implem. Overlay | Cleared | 3/13/2025 | WILLIAM REDMON |
| Prkng lot landscape/Water mgmt | Cleared | 3/17/2025 | JACQUELINE TORRES |
| ZA Case | Cleared | 3/17/2025 | JACQUELINE TORRES |
| Historic Resource Verification | Cleared | 4/15/2025 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 4/15/2025 | YASMINE BASHIRI |
| Zoning Plan Check | Cleared | 4/22/2025 | Ronald Greene |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 9/5/2025 | Partial Inspection | ALAN NOVAK |
| Final | 9/12/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 3/5/2026 | Not Ready for Inspection | DAVID TSAU |
| Special/Order Compliance | 3/5/2026 | Conditional Approval | MICHAEL PETRUSKO |