4030 N DEERVALE DR 91403
Certificate Information: 4030 N DEERVALE DR 91403
- Application / Permit
- 24020-10000-02053
- Plan Check / Job No.
- B24LA31773
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Proposed two new site retaining walls
- Permit Issued
- Issued on 2/8/2025
- Issuing Office
- Current Status
- Issued on 2/8/2025
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | JAD BASMA |
| Corrections Issued | 12/2/2024 | JAD BASMA |
| Quality Review Completed | 12/6/2024 | GARO TELMI |
| Plan Check Approved | 2/7/2025 | JAD BASMA |
| Issued | 2/8/2025 | APPLICANT |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 1/22/2025 | DANIEL CORONADO |
| Grading Pre-Inspection | Cleared | 2/7/2025 | JAD BASMA |
Contact Information
| Contractor | Ada Construction Inc; Lic. No.: 925998-B | , |
| Contractor | Quality Builders La; Lic. No.: 925998-B | , |
| Engineer | Melnyk,, Matthew; Lic. No.: NA5853 | , |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/24/2025 | Conditional Approval | JUAN VALENZUELA |
| Piling/Pier/Caisson | 2/25/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/26/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/27/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 3/24/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/25/2025 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Partial Approval | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 4/7/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 5/23/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 8/26/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 8/28/2025 | Conditional Approval | JUAN VALENZUELA |