9611 W HIGH RIDGE DR 90210

Certificate Information: 9611 W HIGH RIDGE DR 90210

Application / Permit
24020-10000-02016
Plan Check / Job No.
B24LA31134
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
[ePlan] New retaining wall
Permit Issued
Issued on 2/11/2025
Issuing Office
Current Status
Issued on 2/11/2025

Permit Application Status History

Submitted 11/7/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 MAHNAZ NOURHASHEMI
Corrections Issued 11/26/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 11/27/2024 TU HUA
Applicant returned to address corrections 12/24/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 1/15/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 2/6/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 2/10/2025 MAHNAZ NOURHASHEMI
Issued 2/11/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/26/2024 MAHNAZ NOURHASHEMI
ZA Case Cleared 12/2/2024 JACQUELINE TORRES

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B       ,
Contractor Nandco Construction; Lic. No.: 1044615-B       ,
Engineer Standley,, Craig Erick; Lic. No.: NA87675       ,

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2025 Corrections Issued ROBERT PINA
Excavation/Setback/Form/Re-Bar 7/22/2025 Conditional Approval ROBERT PINA
Masonry Wall/Backfill 8/5/2025 Conditional Approval ROBERT PINA
Deputy Reinf. Masonry 8/8/2025 No Access for Inspection ROBERT PINA
Masonry Wall/Backfill 8/11/2025 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 8/22/2025 Conditional Approval ROBERT PINA
Masonry Wall/Backfill 10/8/2025 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 10/20/2025 Conditional Approval ROBERT PINA