2522 N JUPITER DR 90046

Certificate Information: 2522 N JUPITER DR 90046

Application / Permit
24020-10000-01999
Plan Check / Job No.
B24LA30816
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
ePlan: NEW 81'-10" LENGTH, 3'-6" - 4'-6" HT, 8" THK. CONCRETE RETAINING WALL PER SOILS REPORT AND ENGINEER.
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
Permit Finaled on 6/30/2025

Permit Application Status History

Submitted 11/6/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 JESSE VIDUYA
Corrections Issued 11/27/2024 JESSE VIDUYA
Quality Review Completed 12/4/2024 CHAD DOI
Applicant returned to address corrections 2/5/2025 JESSE VIDUYA
Plan Check Approved 3/4/2025 JESSE VIDUYA
Issued 3/13/2025 APPLICANT
Permit Finaled 6/27/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

ZA Case Cleared 12/11/2024 DALIA MOKAYED
Roof/Waste drainage to street Cleared 12/13/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/19/2024 JUSTIN BICOL
Specific Plan Cleared 1/23/2025 JUDE HERNANDEZ
Grading Pre-Inspection Cleared 3/4/2025 JESSE VIDUYA

Contact Information

Contractor Design Management And Construction Services; Lic. No.: 856999-B       ,
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Tuchscher,, James; Lic. No.: C77649 5318 E 2ND ST., #539      LONG BEACH, CA 90803
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 3/20/2025 Approved ALEXANDER HELFER
Pre-Inspection 3/20/2025 Approved ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 5/5/2025 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 5/7/2025 Corrections Issued ROBERT PINA
Footing/Foundation/Slab 5/7/2025 Not Ready for Inspection ROBERT PINA
Footing/Foundation/Slab 5/13/2025 Not Ready for Inspection ROBERT PINA
Excavation/Setback/Form/Re-Bar 5/19/2025 Partial Approval ROBERT PINA
Footing/Foundation/Slab 5/19/2025 Partial Approval ROBERT PINA
Footing/Foundation/Slab 5/23/2025 Partial Approval ROBERT PINA
Masonry Wall/Backfill 6/4/2025 Approved ROBERT PINA
Final 6/27/2025 Permit Finaled RUSSELL BONVOULOIR