14701 W FRIAR ST 91411

Certificate Information: 14701 W FRIAR ST 91411

Application / Permit
24020-10000-01722
Plan Check / Job No.
B23VN14554
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
eplan NEW COVERED TRASH ENCLOSURE
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO Issued on 8/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 PRANITA SHAH
Assigned to Zoning Architect 11/17/2023 CALEB WONG
Corrections Issued 11/28/2023 PRANITA SHAH
Quality Review Completed 11/29/2023 GARO TELMI
Applicant returned to address corrections 6/6/2024 PRANITA SHAH
Applicant returned to address corrections 7/24/2024 PRANITA SHAH
Applicant returned to address corrections 7/26/2024 PRANITA SHAH
Applicant returned to address corrections 9/12/2024 PRANITA SHAH
Applicant returned to address corrections 11/14/2024 PRANITA SHAH
Plan Check Approved 12/3/2024 PRANITA SHAH
Issued 5/7/2025 APPLICANT
CofO in Progress 8/6/2025 ROBERT DAVIS
Permit Finaled 8/8/2025 JEFFREY DURAN
CofO Issued 8/8/2025 JEFFREY DURAN
Permit Finaled 8/8/2025 JEFFREY DURAN

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Armstrong,, James Edward; Lic. No.: NA22059       ,
Contractor E P I Construction Inc; Lic. No.: 865616-B       ,
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 5/14/2025 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 5/14/2025 Corrections Issued BRIAN KELLY
Footing/Foundation/Slab 5/16/2025 Approved GREGORY POMISH
Deputy Wood Construction 5/19/2025 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved ROBERT DAVIS
Deputy Reinf. Masonry 5/21/2025 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 5/22/2025 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 7/16/2025 Conditional Approval JEFFREY DURAN
Final 7/29/2025 OK to Issue CofO ROBERT DAVIS