30 W BEVERLY PARK TER 90210
Certificate Information: 30 W BEVERLY PARK TER 90210
- Application / Permit
- 24020-10000-01633
- Plan Check / Job No.
- B24LA22914
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- EPLAN New retaining wall
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/3/2025
Permit Application Status History
| Submitted | 9/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/30/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/8/2024 | YOUNG KIM |
| Applicant returned to address corrections | 2/19/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 5/13/2025 | ARSALAN SHABESTARI |
| Issued | 5/16/2025 | APPLICANT |
| Permit Finaled | 10/3/2025 | ROBERT PINA |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 10/22/2024 | ROSALINDA MEZA |
| Tract Map conditions | Cleared | 10/22/2024 | ROSALINDA MEZA |
| Tract Map conditions | Cleared | 10/22/2024 | ROSALINDA MEZA |
| ZA Case | Cleared | 10/22/2024 | ROSALINDA MEZA |
| Tract Map conditions | Cleared | 10/23/2024 | ROSALINDA MEZA |
| Tract Map conditions | Cleared | 11/19/2024 | ROSALINDA MEZA |
| ZI | Cleared | 11/20/2024 | ROSALINDA MEZA |
| Excavation more than 5-ft deep | Cleared | 5/13/2025 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/13/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | , |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 7/22/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Grading | 7/23/2025 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 7/31/2025 | Partial Approval | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Not Ready for Inspection | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Not Ready for Inspection | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 8/21/2025 | Approved | ROBERT PINA |
| Footing/Foundation/Slab | 9/5/2025 | Approved | ROBERT PINA |
| Reinforced Concrete Frame | 9/10/2025 | Approved | ROBERT PINA |
| Final | 10/3/2025 | Permit Finaled | ROBERT PINA |