901 E NEW DOCK ST 90731
Certificate Information: 901 E NEW DOCK ST 90731
- Application / Permit
- 24020-10000-01541
- Plan Check / Job No.
- B24LA20991
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- eplan: Equipment pad and anchoring for installation of (1) 2,000 gal two-compartment aboveground fuel tank for diesel and gasoline. The proposed work will include concrete, & associated tank equipment.
- Permit Issued
- Issued on 11/6/2025
- Issuing Office
- Current Status
- CofO Issued on 4/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 9/19/2024 | LY CHEA |
| Corrections Issued | 9/30/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 10/2/2024 | PRANITA SHAH |
| Plan Check Approved | 10/14/2025 | MICHAEL LOPEZ |
| Issued | 11/6/2025 | APPLICANT |
| Permit Finaled | 4/24/2026 | DAVID TSAU |
| CofO Issued | 4/24/2026 | DAVID TSAU |
| Permit Finaled | 4/24/2026 | DAVID TSAU |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 10/3/2024 | HAROOT AVANESIA |
| Abandoned oil well | Cleared | 8/11/2025 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 8/11/2025 | KURT CORRAL |
| "Q" conditions | Cleared | 8/14/2025 | ROSALINDA MEZA |
| Port of LA Approval | Cleared | 9/11/2025 | MELISSA HARNE |
| Coastal Zone | Cleared | 9/18/2025 | NOAH MCCOY |
| Zoning Plan Check | Cleared | 9/30/2025 | LY CHEA |
Contact Information
| Contractor | Orange Coast Petroleum Equipment Inc; Lic. No.: 841021-A | 1015 N PARKER ST ORANGE, CA 92867 |
| Engineer | Meehan,, Richard Gerard; Lic. No.: C21064 | 29251 BALLOCK ST LAGUNA NIGUEL, CA 92677 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/16/2026 | Conditional Approval | DAVID TSAU |
| Final | 4/10/2026 | Conditional Approval | MICHAEL PETRUSKO |
| METHANE-Rough | 4/10/2026 | Approved | MICHAEL PETRUSKO |
| Reinforced Concrete Frame | 4/10/2026 | Approved | MICHAEL PETRUSKO |