1111 E INDIANA AVE 90291
Certificate Information: 1111 E INDIANA AVE 90291
- Application / Permit
- 24020-10000-01454
- Plan Check / Job No.
- B24LA19236
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- EPLAN: NEW RETAINING WALL PER ENGINEER DESIGN (8' MAX HEIGHT, TOTAL LENGTH = 50 LF).
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Current Status
- Permit Finaled on 11/3/2025
Permit Application Status History
| Submitted | 8/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 8/24/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/9/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/13/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/21/2024 | MADISON ODELL |
| Applicant returned to address corrections | 12/18/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/14/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 2/22/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/13/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 3/21/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 3/27/2025 | MIROOSH KHACHATOORIAN |
| Issued | 4/10/2025 | APPLICANT |
| Permit Finaled | 10/29/2025 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 2/18/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2025 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 3/27/2025 | MIROOSH KHACHATOORIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2025 | Partial Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/1/2025 | Corrections Issued | AL GAMBLE |
| Grading Pre-Inspection | 5/5/2025 | Partial Inspection | AL GAMBLE |
| Footing/Foundation/Slab | 5/7/2025 | Corrections Issued | AL GAMBLE |
| Reinforced Masonry Frame | 5/28/2025 | Partial Inspection | AL GAMBLE |
| Final | 10/29/2025 | Permit Finaled | JESUS RODRIGUEZ |