8833 W CASHIO ST 90035

Certificate Information: 8833 W CASHIO ST 90035

Application / Permit
24020-10000-01128
Plan Check / Job No.
B24LA12641
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Temporary)
Work Description
ePlan: (N) TEMPORARY SHORING
Permit Issued
Issued on 12/4/2024
Issuing Office
Current Status
Permit Finaled on 3/4/2025

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 DANIEL YIP
Corrections Issued 7/6/2024 DANIEL YIP
Quality Review Completed 7/31/2024 PRANITA SHAH
Applicant returned to address corrections 12/3/2024 DANIEL YIP
Plan Check Approved 12/4/2024 DANIEL YIP
Issued 12/4/2024 APPLICANT
Permit Finaled 3/4/2025 ARAM AVEDISIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2024 Corrections Issued MEL KHACHATOURIAN
Deputy Reinf. Concrete 12/13/2024 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 12/13/2024 Corrections Issued BOBBY KEY
Deputy Reinf. Concrete 12/16/2024 Partial Approval SEAN HAUPT
Piling/Pier/Caisson 12/16/2024 Partial Approval SEAN HAUPT
Piling/Pier/Caisson 12/17/2024 Not Ready for Inspection ARAM AVEDISIAN
Final 3/4/2025 Permit Finaled ARAM AVEDISIAN