6223 W FRANKLIN AVE 90028
Certificate Information: 6223 W FRANKLIN AVE 90028
- Application / Permit
- 24020-10000-00809
- Plan Check / Job No.
- B24LA08276
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- 12'1" x 12'5" TRASH AREA (OPEN TO SKY)
- Permit Issued
- Issued on 10/14/2024
- Issuing Office
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 5/9/2024 | SARHAD GHEVANDIAN |
| Corrections Issued | 5/14/2024 | HERNAN ARREOLA |
| Quality Review Completed | 5/15/2024 | ARMEN JIVALAGIAN |
| Plan Check Approved | 7/31/2024 | HERNAN ARREOLA |
| Issued | 10/14/2024 | APPLICANT |
| CofO in Progress | 2/26/2025 | LUIS CCAMACHO |
| CofO Issued | 2/28/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 2/28/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| "D" conditions | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | SARHAD GHEVANDIAN |
| Address approval | Cleared | 6/28/2024 | JUSTIN BICOL |
| DAS Clearance | Cleared | 7/2/2024 | NORLITO MEDRANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Apex G B C Inc; Lic. No.: 896883-B | , |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/3/2024 | Corrections Issued | TIMOTHY POWELL |
| Footing/Foundation/Slab | 12/6/2024 | Partial Approval | LUIS CCAMACHO |
| Reinforced Masonry Frame | 12/17/2024 | Partial Approval | TIMOTHY POWELL |
| Final | 2/20/2025 | Partial Inspection | LUIS CCAMACHO |
| Final | 2/26/2025 | OK to Issue CofO | LUIS CCAMACHO |