2006 S CASTLE HEIGHTS AVE 90034
Certificate Information: 2006 S CASTLE HEIGHTS AVE 90034
- Application / Permit
- 24020-10000-00807
- Plan Check / Job No.
- B24LA09113
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/25/2026
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 5/22/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/24/2024 | KEN GILL |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Applicant returned to address corrections | 10/30/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/5/2024 | SERGIO GUTIERREZ |
| Issued | 11/7/2024 | APPLICANT |
| Permit Finaled | 3/24/2026 | JOHNNY MIRANDA |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/30/2024 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 10/30/2024 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Foroughi,, Mohammad Hossein; Lic. No.: C66179 | 767 NORTH HILL STREET 407 LOS ANGELES, CA 90012 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 2/12/2025 | Approved | AL GAMBLE |
| Pre-Inspection | 2/12/2025 | Approved | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Not Ready for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 3/11/2025 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/12/2025 | Approved | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 4/3/2025 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 4/11/2025 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Concrete | 4/30/2025 | Approved | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 4/30/2025 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/2/2025 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 5/2/2025 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/13/2025 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 5/13/2025 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 6/6/2025 | Partial Approval | ROBERT PINA |
| Footing/Foundation/Slab | 6/6/2025 | Partial Approval | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 6/13/2025 | Approved | AL GAMBLE |
| Final | 2/9/2026 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 2/19/2026 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 3/24/2026 | Permit Finaled | JOHNNY MIRANDA |