2006 S CASTLE HEIGHTS AVE 90034

Certificate Information: 2006 S CASTLE HEIGHTS AVE 90034

Application / Permit
24020-10000-00807
Plan Check / Job No.
B24LA09113
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
Permit Finaled on 3/25/2026

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 SERGIO GUTIERREZ
Corrections Issued 5/22/2024 SERGIO GUTIERREZ
Quality Review Completed 5/24/2024 KEN GILL
Building Plans Picked Up 5/31/2024 APPLICANT
Applicant returned to address corrections 10/30/2024 SERGIO GUTIERREZ
Plan Check Approved 11/5/2024 SERGIO GUTIERREZ
Issued 11/7/2024 APPLICANT
Permit Finaled 3/24/2026 JOHNNY MIRANDA

Permit Application Clearance Information

GPI Written Notices Cleared 10/30/2024 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 10/30/2024 SERGIO GUTIERREZ

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Foroughi,, Mohammad Hossein; Lic. No.: C66179 767 NORTH HILL STREET 407      LOS ANGELES, CA 90012
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 2/12/2025 Approved AL GAMBLE
Pre-Inspection 2/12/2025 Approved AL GAMBLE
Excavation/Setback/Form/Re-Bar 3/4/2025 Not Ready for Inspection AL GAMBLE
Excavation/Setback/Form/Re-Bar 3/11/2025 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 3/12/2025 Approved AL GAMBLE
Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 4/11/2025 Partial Approval AL GAMBLE
Deputy Reinf. Concrete 4/30/2025 Approved AL GAMBLE
Excavation/Setback/Form/Re-Bar 4/30/2025 Partial Approval AL GAMBLE
Footing/Foundation/Slab 4/30/2025 Partial Approval AL GAMBLE
Excavation/Setback/Form/Re-Bar 5/2/2025 Partial Approval AL GAMBLE
Footing/Foundation/Slab 5/2/2025 Partial Approval AL GAMBLE
Excavation/Setback/Form/Re-Bar 5/13/2025 Partial Approval AL GAMBLE
Footing/Foundation/Slab 5/13/2025 Partial Approval AL GAMBLE
Excavation/Setback/Form/Re-Bar 5/19/2025 Partial Approval AL GAMBLE
Excavation/Setback/Form/Re-Bar 5/30/2025 Partial Approval AL GAMBLE
Footing/Foundation/Slab 5/30/2025 Partial Approval AL GAMBLE
Excavation/Setback/Form/Re-Bar 6/6/2025 Partial Approval ROBERT PINA
Footing/Foundation/Slab 6/6/2025 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 6/13/2025 Partial Approval AL GAMBLE
Footing/Foundation/Slab 6/13/2025 Approved AL GAMBLE
Final 2/9/2026 Not Ready for Inspection JESUS RODRIGUEZ
Final 2/19/2026 Not Ready for Inspection JOHNNY MIRANDA
Final 3/24/2026 Permit Finaled JOHNNY MIRANDA