8141 S GULANA AVE 90293

Certificate Information: 8141 S GULANA AVE 90293

Application / Permit
24020-10000-00774
Plan Check / Job No.
B24LA08725
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
EPLAN: NEW PREMANUFACTURED GUARD SHACK.
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
Issued on 11/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/9/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 PRANITA SHAH
Assigned to Zoning Architect 5/23/2024 CALEB WONG
Corrections Issued 6/24/2024 PRANITA SHAH
Quality Review Completed 7/15/2024 MICHAEL PEREZ
Applicant returned to address corrections 8/27/2024 PRANITA SHAH
Applicant returned to address corrections 10/15/2024 PRANITA SHAH
Plan Check Approved 11/12/2024 PRANITA SHAH
Issued 11/12/2024 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 6/12/2024 DANIEL CORONADO
Miscellaneous Cleared 6/12/2024 DANIEL CORONADO
Miscellaneous Cleared 6/12/2024 DANIEL CORONADO
ZA Case Cleared 6/12/2024 DANIEL CORONADO
ZA Case Cleared 6/12/2024 DANIEL CORONADO
ZA Case Cleared 6/12/2024 DANIEL CORONADO
ZA Case Cleared 6/12/2024 DANIEL CORONADO
Coastal Zone Cleared 7/16/2024 DANIEL CORONADO
Specific Plan Cleared 8/6/2024 FREDDY GARCIA
CPC Cleared 8/8/2024 DANIEL CORONADO
Zoning Plan Check Cleared 8/14/2024 Jesse Arellano
Abandoned oil well Cleared 10/9/2024 JERRY KAO

Contact Information

Contractor Cnc Builders Inc; Lic. No.: 1038564-B       ,

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2025 Partial Approval DERRICK SPENCER
Final 2/7/2025 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 2/7/2025 Approved DERRICK SPENCER
Green Building Final 2/7/2025 Approved DERRICK SPENCER
Green Building Rough 2/7/2025 Approved DERRICK SPENCER
METHANE-Barrier 2/7/2025 Approved DERRICK SPENCER
METHANE-Final 2/7/2025 Approved DERRICK SPENCER
METHANE-Rough 2/7/2025 Approved DERRICK SPENCER
METHANE-Subgrade 2/7/2025 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV No Gas DERRICK SPENCER
Smoke Detectors 2/7/2025 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 2/7/2025 Approved DERRICK SPENCER
Wood Frame 2/7/2025 Approved DERRICK SPENCER
Final 2/21/2025 Partial Approval DERRICK SPENCER
Final 2/26/2025 Not Ready for Inspection DERRICK SPENCER
Final 3/10/2025 Not Ready for Inspection DERRICK SPENCER