8141 S GULANA AVE 90293
Certificate Information: 8141 S GULANA AVE 90293
- Application / Permit
- 24020-10000-00774
- Plan Check / Job No.
- B24LA08725
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- EPLAN: NEW PREMANUFACTURED GUARD SHACK.
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- Issued on 11/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | PRANITA SHAH |
| Assigned to Zoning Architect | 5/23/2024 | CALEB WONG |
| Corrections Issued | 6/24/2024 | PRANITA SHAH |
| Quality Review Completed | 7/15/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/27/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 10/15/2024 | PRANITA SHAH |
| Plan Check Approved | 11/12/2024 | PRANITA SHAH |
| Issued | 11/12/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/12/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 6/12/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 6/12/2024 | DANIEL CORONADO |
| Coastal Zone | Cleared | 7/16/2024 | DANIEL CORONADO |
| Specific Plan | Cleared | 8/6/2024 | FREDDY GARCIA |
| CPC | Cleared | 8/8/2024 | DANIEL CORONADO |
| Zoning Plan Check | Cleared | 8/14/2024 | Jesse Arellano |
| Abandoned oil well | Cleared | 10/9/2024 | JERRY KAO |
Contact Information
| Contractor | Cnc Builders Inc; Lic. No.: 1038564-B | , |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Partial Approval | DERRICK SPENCER |
| Final | 2/7/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/7/2025 | Approved | DERRICK SPENCER |
| Green Building Final | 2/7/2025 | Approved | DERRICK SPENCER |
| Green Building Rough | 2/7/2025 | Approved | DERRICK SPENCER |
| METHANE-Barrier | 2/7/2025 | Approved | DERRICK SPENCER |
| METHANE-Final | 2/7/2025 | Approved | DERRICK SPENCER |
| METHANE-Rough | 2/7/2025 | Approved | DERRICK SPENCER |
| METHANE-Subgrade | 2/7/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV No Gas | DERRICK SPENCER |
| Smoke Detectors | 2/7/2025 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 2/7/2025 | Approved | DERRICK SPENCER |
| Wood Frame | 2/7/2025 | Approved | DERRICK SPENCER |
| Final | 2/21/2025 | Partial Approval | DERRICK SPENCER |
| Final | 2/26/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 3/10/2025 | Not Ready for Inspection | DERRICK SPENCER |