2012 N ALVARADO ST 90039

Certificate Information: 2012 N ALVARADO ST 90039

Application / Permit
24020-10000-00686
Plan Check / Job No.
B24LA07613
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
E-plan. Two new retaining walls within side yards (see site plan for location)
Permit Issued
Issued on 9/8/2025
Issuing Office
Current Status
Issued on 9/8/2025

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 MARCELA FRANQUEZ
Corrections Issued 5/11/2024 MARCELA FRANQUEZ
Quality Review Completed 5/23/2024 TU HUA
Applicant returned to address corrections 8/21/2024 MARCELA FRANQUEZ
Applicant returned to address corrections 10/21/2024 MARCELA FRANQUEZ
Plan Check Approved 9/8/2025 MARCELA FRANQUEZ
Issued 9/8/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/13/2024 MARCELA FRANQUEZ
Eng Process Fee Ord 176,300 Cleared 9/24/2024 JEANIE LAM
Encroachment in public way Cleared 10/4/2024 MARK REYES

Contact Information

Contractor Red Stag Construction Company; Lic. No.: 964664-B       ,
Engineer Bermejo,, Gil Banzon; Lic. No.: C86264 2308 MOUNTAIN OAK RD      BAKERSFIELD, CA 93311
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 11/5/2025 Corrections Issued HAMIK HARTOUNIAN
Deputy Reinf. Concrete 11/7/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 11/12/2025 Conditional Approval OSVALDO PARAMO
Deputy Reinf. Concrete 4/14/2026 Conditional Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 4/15/2026 Partial Inspection JONATHAN HOM
Piling/Pier/Caisson 4/17/2026 Partial Approval JONATHAN HOM
Deputy Drilled-In Anchors 5/20/2026 Approved JONATHAN HOM
Deputy Drilled-In Anchors 5/27/2026 Approved JONATHAN HOM
Deputy Reinf. Concrete 5/27/2026 Approved JONATHAN HOM
Deputy Other (see comments) 5/29/2026 Approved JONATHAN HOM
Deputy Reinf. Concrete 6/30/2026 Conditional Approval JONATHAN HOM
Deputy Reinf. Concrete 7/2/2026 Approved JONATHAN HOM