1115 N MORAGA DR 90049

Certificate Information: 1115 N MORAGA DR 90049

Application / Permit
24020-10000-00548
Plan Check / Job No.
B24LA03459
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
ePlan: New retaining walls for (n) pool and deck
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
Issued on 8/29/2024

Permit Application Status History

Submitted 3/7/2024 APPLICANT
Assigned to Plan Check Engineer 3/14/2024 KHEDER ALRAZAA
Corrections Issued 4/4/2024 ADRIANA LOPEZ
Quality Review Completed 4/10/2024 GARO TELMI
Plan Check Approved 8/29/2024 KHEDER ALRAZAA
Issued 8/29/2024 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 4/23/2024 FIPE LEILUA
Excavation more than 5-ft deep Cleared 8/29/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 8/29/2024 ADRIANA LOPEZ

Contact Information

Architect Borghei,, Mo; Lic. No.: C17777 12249 DOROTHY STREET      LOS ANGELES, CA 90049
Contractor Lehigh Inc; Lic. No.: 714358-B 714 S PLYMOUTH BLVD      LOS ANGELES, CA 90005
Engineer Masud,, Fahad Mohammed; Lic. No.: C92662 2415 EATON COURT      ORANGE, CA 92867
Engineer Rahbar,, Farzin S; Lic. No.: S2833 20812 VENTURA BLVD 200      WOODLAND HILLS, CA 91364
Geologist Stone,, Andrew; Lic. No.: EG1648 180 WHITE RIVER LANE      CORONA, CA 92881

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2024 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 9/13/2024 Conditional Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 9/17/2024 No Access for Inspection VASIL MIHALEV
Deputy Drilled-In Anchors 9/23/2024 No Access for Inspection MATTHEW JENKINS
Footing/Foundation/Slab 9/24/2024 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 9/26/2024 Approved ALEXANDER HELFER
Footing/Foundation/Slab 10/3/2024 Partial Approval AL GAMBLE
Deputy Reinf. Concrete 10/4/2024 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 10/9/2024 Not Ready for Inspection JOHNNY MIRANDA
Deputy Shotcrete 10/10/2024 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 10/11/2024 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 10/15/2024 Conditional Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 10/25/2024 Conditional Approval AL GAMBLE
Deputy Reinf. Concrete 10/25/2024 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 10/25/2024 Partial Approval MATTHEW JENKINS
Deputy Reinf. Concrete 10/28/2024 No Access for Inspection VASIL MIHALEV
Deputy Reinf. Concrete 11/4/2024 Conditional Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 12/16/2024 Conditional Approval MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 2/11/2025 Partial Inspection MATTHEW JENKINS
Footing/Foundation/Slab 2/11/2025 Partial Inspection MATTHEW JENKINS
Deputy Reinf. Concrete 2/12/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 2/18/2025 Conditional Approval MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 5/5/2025 Not Ready for Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 5/8/2025 Partial Inspection MATTHEW JENKINS
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Inspection MATTHEW JENKINS