1648 N EL CENTRO AVE 90028
Certificate Information: 1648 N EL CENTRO AVE 90028
- Application / Permit
- 24019-10000-01577
- Plan Check / Job No.
- B24LA07164
- Group
- Building
- Type
- Bldg-Demolition
- Sub-Type
- Commercial
- Primary Use
- (7) Garage - Private
- Work Description
- DEMOLISH (E) DETACHED GARAGE
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/29/2025
Permit Application Status History
| Submitted | 4/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 4/26/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/14/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 9/26/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/10/2024 | SERGIO MUNIZ |
| Plan Check Approved | 10/21/2024 | SERGIO MUNIZ |
| Issued | 11/8/2024 | APPLICANT |
| Permit Finaled | 1/28/2025 | JEFFREY FULTON |
Permit Application Clearance Information
| "D" conditions | Cleared | 8/1/2024 | DAVID URITA |
| CPC | Cleared | 8/1/2024 | DAVID URITA |
| ZA Case | Cleared | 8/1/2024 | DAVID URITA |
| Metro Rail approval | Cleared | 8/5/2024 | JENNIFER SU |
| Address approval | Cleared | 8/8/2024 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2024 | JOSE HERNANDEZ |
| DPI Written Notices | Cleared | 9/29/2024 | DAVID BURKHEAD |
| Demolition | Cleared | 9/29/2024 | LIKYELESH ABERA |
| Redevelopment Project Area | Cleared | 10/1/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Greenleaf Engineering; Lic. No.: 789510-B | 18685 MAIN STREET A-371 HUNTINGTON BEACH, CA 92648 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Demo Pre-Inspection | 11/21/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Demo Pre-Inspection | 11/27/2024 | Approved | DAVID BURKHEAD |
| Protection Fence/Barricades | 11/27/2024 | Approved | DAVID BURKHEAD |
| Final | 1/15/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 1/28/2025 | Permit Finaled | JEFFREY FULTON |