3010 S SEPULVEDA BLVD 90034

Certificate Information: 3010 S SEPULVEDA BLVD 90034

Application / Permit
24016-70000-24977
Plan Check / Job No.
B24SL00534
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
Site improvements to restripe parking lot and create accessible parking stalls. Upgrade walkways and ramps for accessible route.
Permit Issued
Issued on 10/10/2025
Issuing Office
Metro
Current Status
Permit Finaled on 2/18/2026

Permit Application Status History

Submitted 8/6/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 SINA KHOSRAVI
Assigned to Zoning Architect 8/8/2024 JASON BRAVO
Corrections Issued 8/15/2024 SINA KHOSRAVI
Quality Review Completed 9/4/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 9/19/2025 SINA KHOSRAVI
Plan Check Approved 9/23/2025 SINA KHOSRAVI
Issued 10/10/2025 APPLICANT
Permit Finaled 2/18/2026 FARHAD DADBIN

Permit Application Clearance Information

Miscellaneous Cleared 4/14/2025 JASON CHAN
Miscellaneous Cleared 4/14/2025 JASON CHAN
Miscellaneous Cleared 4/14/2025 JASON CHAN
Grading Pre-Inspection Cleared 4/15/2025 LANNY MERRICK
DAS Clearance Cleared 8/15/2025 SINA KHOSRAVI
Low Impact Development (LID) Cleared 8/19/2025 MARTIN FRAGOSO
Zoning Plan Check Cleared 9/2/2025 SINA KHOSRAVI

Contact Information

Contractor International Paving Services Inc; Lic. No.: 770392-B P O BOX 10458      SAN BERNARDINO, CA 92423
Engineer Johnson,, Tyler Hilding; Lic. No.: C85839 1275 HAVENHURST DR APT 18      WEST HOLLYWOOD, CA 90046

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/28/2025 Approved FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 11/5/2025 Partial Approval FARHAD DADBIN
Pre-Inspection 11/5/2025 Approved FARHAD DADBIN
Footing/Foundation/Slab 11/7/2025 Partial Approval FARHAD DADBIN
Pre-Inspection 11/7/2025 Approved FARHAD DADBIN
Pre-Inspection 11/24/2025 Partial Approval FARHAD DADBIN
Pre-Inspection 11/25/2025 Approved FARHAD DADBIN
Pre-Inspection 11/26/2025 Partial Approval FARHAD DADBIN
Pre-Inspection 12/3/2025 Approved VASIL MIHALEV
Pre-Inspection 12/4/2025 Approved VASIL MIHALEV
Pre-Inspection 12/5/2025 Partial Approval FARHAD DADBIN
Final 2/18/2026 Permit Finaled FARHAD DADBIN
Footing/Foundation/Slab 2/18/2026 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 2/18/2026 Approved FARHAD DADBIN