3010 S SEPULVEDA BLVD 90034
Certificate Information: 3010 S SEPULVEDA BLVD 90034
- Application / Permit
- 24016-70000-24977
- Plan Check / Job No.
- B24SL00534
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Site improvements to restripe parking lot and create accessible parking stalls. Upgrade walkways and ramps for accessible route.
- Permit Issued
- Issued on 10/10/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/18/2026
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | SINA KHOSRAVI |
| Assigned to Zoning Architect | 8/8/2024 | JASON BRAVO |
| Corrections Issued | 8/15/2024 | SINA KHOSRAVI |
| Quality Review Completed | 9/4/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/19/2025 | SINA KHOSRAVI |
| Plan Check Approved | 9/23/2025 | SINA KHOSRAVI |
| Issued | 10/10/2025 | APPLICANT |
| Permit Finaled | 2/18/2026 | FARHAD DADBIN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/14/2025 | JASON CHAN |
| Miscellaneous | Cleared | 4/14/2025 | JASON CHAN |
| Miscellaneous | Cleared | 4/14/2025 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 4/15/2025 | LANNY MERRICK |
| DAS Clearance | Cleared | 8/15/2025 | SINA KHOSRAVI |
| Low Impact Development (LID) | Cleared | 8/19/2025 | MARTIN FRAGOSO |
| Zoning Plan Check | Cleared | 9/2/2025 | SINA KHOSRAVI |
Contact Information
| Contractor | International Paving Services Inc; Lic. No.: 770392-B | P O BOX 10458 SAN BERNARDINO, CA 92423 |
| Engineer | Johnson,, Tyler Hilding; Lic. No.: C85839 | 1275 HAVENHURST DR APT 18 WEST HOLLYWOOD, CA 90046 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/28/2025 | Approved | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 11/5/2025 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 11/7/2025 | Approved | FARHAD DADBIN |
| Pre-Inspection | 11/24/2025 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 11/25/2025 | Approved | FARHAD DADBIN |
| Pre-Inspection | 11/26/2025 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 12/3/2025 | Approved | VASIL MIHALEV |
| Pre-Inspection | 12/4/2025 | Approved | VASIL MIHALEV |
| Pre-Inspection | 12/5/2025 | Partial Approval | FARHAD DADBIN |
| Final | 2/18/2026 | Permit Finaled | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/18/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/18/2026 | Approved | FARHAD DADBIN |