1189 E 56TH ST 90011

Certificate Information: 1189 E 56TH ST 90011

Application / Permit
24016-70000-03379
Plan Check / Job No.
B24SL00017
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached storage and grage building to an ADU per state law.
Permit Issued
Issued on 4/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2024 APPLICANT
Corrections Issued 2/6/2024 RICARDO RAMIREZ
Assigned to Plan Check Engineer 2/7/2024 RICARDO RAMIREZ
Corrections Issued 2/7/2024 RICARDO RAMIREZ
Building Plans Picked Up 2/13/2024 APPLICANT
Applicant returned to address corrections 2/29/2024 RICARDO RAMIREZ
Plan Check Approved 4/2/2024 RICARDO RAMIREZ
Issued 4/22/2024 APPLICANT
CofO in Progress 4/17/2025 ALEJANDRO DE ARTOLA
No Progress 4/20/2025 DEROLD HAUFF
CofO in Progress 4/20/2025 DEROLD HAUFF
Permit Finaled 4/25/2025 DEROLD HAUFF
CofO Issued 4/25/2025 DEROLD HAUFF
Permit Finaled 4/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 2/21/2024 MARIA VENDIVIL
Address approval Cleared 2/22/2024 CHRISTINA BRACO
Sewer availability Cleared 2/22/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/5/2024 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 3/27/2024 ANACANY HURTADO
ZI Cleared 3/27/2024 ANACANY HURTADO

Contact Information

Contractor J&C Builders Inc; Lic. No.: 1100257-B 2900 CEDAR AVE      LONG BEACH, CA 90806

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 6/25/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/25/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/28/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/18/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/23/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/23/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 11/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/27/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/27/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/27/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 11/27/2024 Approved ALEJANDRO DE ARTOLA
Insulation 12/6/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/6/2024 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 12/6/2024 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 12/9/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/9/2024 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 12/9/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/23/2024 Approved ALEJANDRO DE ARTOLA
Final 2/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 2/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 2/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 2/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 2/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/8/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 4/8/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/14/2025 Approved ALEJANDRO DE ARTOLA
Final 4/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/14/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/14/2025 Approved ALEJANDRO DE ARTOLA
Final 4/16/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 4/16/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/16/2025 Approved ALEJANDRO DE ARTOLA