1101 W COLORADO BLVD 90041

Certificate Information: 1101 W COLORADO BLVD 90041

Application / Permit
24016-40000-17796
Plan Check / Job No.
B24SP00110
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Music School or Studio
Work Description
TENANT IMPROVEMENT TO EXISTING OFFICE BUILDING TO CREATE MUSIC STUDIO
Permit Issued
Issued on 12/24/2024
Issuing Office
Valley
Current Status
Issued on 12/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 MARCELA FRANQUEZ
Assigned to Zoning Architect 6/6/2024 SARHAD GHEVANDIAN
Corrections Issued 6/14/2024 MARCELA FRANQUEZ
Quality Review Completed 6/21/2024 KEN GILL
Building Plans Picked Up 6/26/2024 APPLICANT
Disabled Access Plans Picked Up 7/29/2024 APPLICANT
Green Plans Picked Up 12/16/2024 APPLICANT
Applicant returned to address corrections 12/18/2024 MARCELA FRANQUEZ
Plan Check Approved 12/20/2024 MARCELA FRANQUEZ
Issued 12/24/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/7/2024 MICHAEL TEMPLE
Address approval Cleared 10/29/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 10/29/2024 JILVER MAZARIEGOS
Sewer availability Cleared 10/29/2024 JILVER MAZARIEGOS
"Q" conditions Cleared 11/7/2024 DAVID URITA
Zoning Plan Check Cleared 11/25/2024 SARHAD GHEVANDIAN
DAS Clearance Cleared 12/3/2024 SHINE LIN
Green Code Cleared 12/19/2024 AARON COSTA

Contact Information

Architect Browning,, Jeffrey Carleton; Lic. No.: C34782 1570 WEST 9TH STREET      SAN PEDRO, CA 90732
Contractor Mora Woodcraft; Lic. No.: 985928-B 2320 EAST CENTRAL AVENUE #16      DUARTE, CA 91010
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Approved RONALD JIMENEZ
Masonry Wall/Backfill 4/17/2025 Approved RONALD JIMENEZ
Wood Frame 4/17/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 4/29/2025 Approved RAFAEL CORTES
Reinforced Masonry Frame 5/8/2025 Approved RONALD JIMENEZ
Footing/Foundation/Slab 5/28/2025 Partial Approval JEROME BLACKWOOD
Special/Order Compliance 6/6/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 9/17/2025 Approved RONALD JIMENEZ
Insulation 9/18/2025 Partial Approval RONALD JIMENEZ
Wood Frame 9/19/2025 No Access for Inspection RAFAEL CORTES
Insulation 10/3/2025 Approved RONALD JIMENEZ
Drywall Nailing 10/24/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 10/27/2025 Approved RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 12/9/2025 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 12/16/2025 Partial Approval RONALD JIMENEZ
Masonry Wall/Backfill 12/30/2025 Approved RONALD JIMENEZ
Pre-Inspection 1/8/2026 Approved RONALD JIMENEZ
Pre-Inspection 1/15/2026 Approved RAFAEL CORTES