737-741 W 22ND ST 90731
Certificate Information: 737-741 W 22ND ST 90731
- Application / Permit
- 24016-40000-14668
- Plan Check / Job No.
- B24SP00090
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT UNUSED UNDERFLOOR SPACE INTO A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/8/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/14/2024 | APPLICANT |
| Applicant returned to address corrections | 5/23/2024 | SERGIO SILVA |
| Plan Check Approved | 8/6/2024 | TSE MING HUANG |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 12/26/2024 | PAUL REECE |
| Permit Finaled | 1/29/2025 | CLAUDIO MORENO |
| CofO Issued | 1/29/2025 | CLAUDIO MORENO |
| Permit Finaled | 1/29/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2024 | KHAING AYE |
| Sewer availability | Cleared | 6/6/2024 | KHAING AYE |
Contact Information
| Contractor | Orr Industries Inc; Lic. No.: 1028720-B | 1977 OBISPO AVE SIGNAL HILL, CA 90755 |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 10/15/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 10/16/2024 | Not Ready for Inspection | PAUL REECE |
| ELECTRICAL-Rough | 11/14/2024 | Approved | PAUL REECE |
| HVAC-Rough | 11/14/2024 | Corrections Issued | PAUL REECE |
| Light Gage Steel Frame | 11/14/2024 | Approved | PAUL REECE |
| PLUMBING-Rough | 11/14/2024 | Approved | PAUL REECE |
| Drywall Nailing | 11/20/2024 | Approved | PAUL REECE |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | PAUL REECE |
| Final | 12/4/2024 | Corrections Issued | PAUL REECE |
| Footing/Foundation/Slab | 12/4/2024 | Corrections Issued | PAUL REECE |
| Green Building Final | 12/4/2024 | Approved | PAUL REECE |
| Green Building Rough | 12/4/2024 | Approved | PAUL REECE |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | PAUL REECE |
| Smoke Detectors | 12/4/2024 | Approved | PAUL REECE |
| Final | 12/23/2024 | OK to Issue CofO | PAUL REECE |