737-741 W 22ND ST 90731

Certificate Information: 737-741 W 22ND ST 90731

Application / Permit
24016-40000-14668
Plan Check / Job No.
B24SP00090
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT UNUSED UNDERFLOOR SPACE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 10/9/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2024 APPLICANT
Assigned to Plan Check Engineer 5/7/2024 LAWRENCE QUIRANTE
Corrections Issued 5/8/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 5/14/2024 APPLICANT
Applicant returned to address corrections 5/23/2024 SERGIO SILVA
Plan Check Approved 8/6/2024 TSE MING HUANG
Issued 10/9/2024 APPLICANT
CofO in Progress 12/26/2024 PAUL REECE
Permit Finaled 1/29/2025 CLAUDIO MORENO
CofO Issued 1/29/2025 CLAUDIO MORENO
Permit Finaled 1/29/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 5/29/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 6/6/2024 KHAING AYE
Sewer availability Cleared 6/6/2024 KHAING AYE

Contact Information

Contractor Orr Industries Inc; Lic. No.: 1028720-B 1977 OBISPO AVE      SIGNAL HILL, CA 90755
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 10/15/2024 Not Ready for Inspection JOSEPH MCGARRY
Insulation 10/16/2024 Not Ready for Inspection PAUL REECE
ELECTRICAL-Rough 11/14/2024 Approved PAUL REECE
HVAC-Rough 11/14/2024 Corrections Issued PAUL REECE
Light Gage Steel Frame 11/14/2024 Approved PAUL REECE
PLUMBING-Rough 11/14/2024 Approved PAUL REECE
Drywall Nailing 11/20/2024 Approved PAUL REECE
BUILDING-Rough-Frame 12/4/2024 Approved PAUL REECE
Final 12/4/2024 Corrections Issued PAUL REECE
Footing/Foundation/Slab 12/4/2024 Corrections Issued PAUL REECE
Green Building Final 12/4/2024 Approved PAUL REECE
Green Building Rough 12/4/2024 Approved PAUL REECE
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Approved PAUL REECE
Smoke Detectors 12/4/2024 Approved PAUL REECE
Final 12/23/2024 OK to Issue CofO PAUL REECE