566 W 26TH ST 1-3 90731
Certificate Information: 566 W 26TH ST 1-3 90731
- Application / Permit
- 24016-40000-08529
- Plan Check / Job No.
- B24SP00048
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 1ST FLOOR GARAGE INTO A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- San Pedro
- Current Status
- Issued on 8/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/16/2024 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/2/2024 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/9/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 7/23/2024 | LAWRENCE QUIRANTE |
| Issued | 8/1/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | KHAING AYE |
| Sewer availability | Cleared | 4/22/2024 | KHAING AYE |
| Address approval | Cleared | 4/23/2024 | KHAING AYE |
| Grading Pre-Inspection | Cleared | 5/8/2024 | AL GAMBLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/20/2024 | Approved | ANSON MAGLASANG |
| Green Building Rough | 11/7/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 11/7/2024 | Partial Inspection | JOSEPH MCGARRY |
| Insulation | 11/25/2024 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Wood Frame | 12/23/2024 | Approved | JOSEPH MCGARRY |
| Final | 2/5/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 2/5/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 2/5/2025 | Approved | JOSEPH MCGARRY |