4327-4331 1/4 W AVOCADO ST 90027

Certificate Information: 4327-4331 1/4 W AVOCADO ST 90027

Application / Permit
24016-30001-06682
Plan Check / Job No.
B24WL07678
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(5) Apartment
Work Description
Supplemental ref to pcis # 24016-10000-06682, to change lower level ADU from a 1 bedroom to 2-bedroom unit and for structural revisions to foundation and framing plan.
Permit Issued
Issued on 10/17/2024
Issuing Office
Metro
Current Status
Permit Finaled on 5/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2024 APPLICANT
Assigned to Plan Check Engineer 10/2/2024 RICHARD GARCIA
Corrections Issued 10/5/2024 RICHARD GARCIA
Building Plans Picked Up 10/8/2024 APPLICANT
Plan Check Approved 10/11/2024 DAVID CASTILLO
Issued 10/17/2024 APPLICANT
Permit Finaled 5/7/2025 NICHOLAS LOPEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/11/2024 DARIN LAM
Sewer availability Cleared 10/11/2024 DARIN LAM

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 11/5/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/7/2024 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 11/7/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/18/2024 Approved BRENDAN MORELLI
ELECTRICAL-Rough 11/25/2024 No Access for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/10/2025 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/14/2025 Corrections Issued JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 1/16/2025 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/24/2025 Corrections Issued JOAQUIN GREENOUGH
Insulation 1/24/2025 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 1/24/2025 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/28/2025 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 1/28/2025 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 1/31/2025 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 1/31/2025 Corrections Issued ENRIQUE MIRELES
Drywall Nailing 2/10/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/21/2025 Approved ENRIQUE MIRELES
Final 3/21/2025 Corrections Issued ENRIQUE MIRELES
HVAC-Final 3/21/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 3/21/2025 Approved ENRIQUE MIRELES
Smoke Detectors 3/21/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/27/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 3/27/2025 Corrections Issued ENRIQUE MIRELES
HVAC-Final 3/27/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 3/27/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/1/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 4/24/2025 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 5/7/2025 Approved NICHOLAS LOPEZ
Final 5/7/2025 Permit Finaled NICHOLAS LOPEZ