4327-4331 1/4 W AVOCADO ST 90027
Certificate Information: 4327-4331 1/4 W AVOCADO ST 90027
- Application / Permit
- 24016-30001-06682
- Plan Check / Job No.
- B24WL07678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (5) Apartment
- Work Description
- Supplemental ref to pcis # 24016-10000-06682, to change lower level ADU from a 1 bedroom to 2-bedroom unit and for structural revisions to foundation and framing plan.
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2024 | RICHARD GARCIA |
| Corrections Issued | 10/5/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 10/8/2024 | APPLICANT |
| Plan Check Approved | 10/11/2024 | DAVID CASTILLO |
| Issued | 10/17/2024 | APPLICANT |
| Permit Finaled | 5/7/2025 | NICHOLAS LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2024 | DARIN LAM |
| Sewer availability | Cleared | 10/11/2024 | DARIN LAM |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/5/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/7/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/7/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/18/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/25/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 1/10/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 1/14/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 1/16/2025 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/24/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 1/24/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/24/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 1/28/2025 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 1/31/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/31/2025 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 2/10/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/21/2025 | Approved | ENRIQUE MIRELES |
| Final | 3/21/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 3/21/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/21/2025 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/21/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/27/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 3/27/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 3/27/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 3/27/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/1/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/24/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/7/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/7/2025 | Permit Finaled | NICHOLAS LOPEZ |