151-153 W 51ST PL 90037

Certificate Information: 151-153 W 51ST PL 90037

Application / Permit
24016-30000-40044
Plan Check / Job No.
B24WL09960
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Remodel unit 1F on first floor of an (E) non-sprinklered two-story duplex and convert 525 sf portion of unit 1F into an ADU per LAMC 12.22A33(c) & (e). Relocate kitchen on 2nd floor and add a bedroom. "COMPLY WITH DEPARTMENT ORDER effective date 04/18/2014. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/24/2025
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 JAHANSHAH POURHASSAN
Corrections Issued 12/20/2024 JAHANSHAH POURHASSAN
Building Plans Picked Up 12/26/2024 APPLICANT
Plan Check Approved 2/14/2025 JAHANSHAH POURHASSAN
Issued 2/24/2025 APPLICANT
CofO in Progress 10/6/2025 BRIAN SULLIVAN
Permit Finaled 10/7/2025 DEROLD HAUFF
CofO Issued 10/7/2025 DEROLD HAUFF
Permit Finaled 10/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/30/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 12/30/2024 JUSTIN BICOL
Sewer availability Cleared 12/30/2024 JUSTIN BICOL
Tenant Habitability Plan Cleared 12/31/2024 RICARDO BOHORQUEZ
Flood clearance Cleared 2/4/2025 SAMSON WONG

Contact Information

Contractor Mamos Construction & Design; Lic. No.: 1092889-B 5134 ALLENTOWN PLACE      WOODLAND HILLS, CA 91364

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/30/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 4/30/2025 Partial Approval LUIS CASTRO
HVAC-Rough 5/12/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 5/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 6/9/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 6/9/2025 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 8/6/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/6/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Final 8/6/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/6/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 8/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/11/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/19/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 8/19/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/19/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/22/2025 Approved ALEJANDRO DE ARTOLA
Final 8/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/22/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/22/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/22/2025 Approved ALEJANDRO DE ARTOLA
Final 8/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/25/2025 Approved ALEJANDRO DE ARTOLA
Final 9/29/2025 No Access for Inspection BARRY HACHE
Final 10/1/2025 No Access for Inspection ENRIQUE MIRELES
Final 10/3/2025 OK to Issue CofO MICHAEL LEWIS