1153 S ORLANDO AVE 90035
Certificate Information: 1153 S ORLANDO AVE 90035
- Application / Permit
- 24016-30000-38537
- Plan Check / Job No.
- B24WL09498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage into an ADU per GC 66323(a)(1) in the rear of the lot.
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | KAVIAN REFAHI |
| Corrections Issued | 12/6/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 12/17/2024 | APPLICANT |
| Applicant returned to address corrections | 6/9/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 8/27/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 9/8/2025 | JAHANSHAH POURHASSAN |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/3/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | MICHELLE RIOS |
| City Hist. Cultural Monument | Cleared | 6/27/2025 | DEBORAH MCGILL |
| HPOZ | Cleared | 6/27/2025 | DEBORAH MCGILL |
| Historic monument | Cleared | 6/27/2025 | DEBORAH MCGILL |
| ZA Case | Cleared | 6/27/2025 | DEBORAH MCGILL |
| Construction within easement | Cleared | 7/31/2025 | RIDWAN HARDY |
| CPC | Cleared | 8/22/2025 | ALEX VELA |
| ZA Case | Cleared | 8/22/2025 | ALEX VELA |
| ZA Case | Cleared | 8/22/2025 | ALEX VELA |
| ZA Case | Cleared | 8/22/2025 | ALEX VELA |
| ZA Case | Cleared | 8/22/2025 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Kunyoung; Lic. No.: C66880 | 22812 ERIEL AVE TORRANCE, CA 90505 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/6/2026 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/25/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 3/25/2026 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 5/12/2026 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 5/12/2026 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 5/12/2026 | Approved | DAVID WILLIAMS |
| METHANE-Rough | 5/12/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 5/12/2026 | Approved | DAVID WILLIAMS |
| Insulation | 5/14/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/14/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 5/19/2026 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 5/19/2026 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/28/2026 | Approved | DAVID WILLIAMS |