1523 N STRADELLA ROAD 90077
Certificate Information: 1523 N STRADELLA ROAD 90077
- Application / Permit
- 24016-30000-37391
- Plan Check / Job No.
- B24WL09240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REPAIR AND OR REPLACEMENT OF WATERPROOFING AT ROOF, WALLS DECKS AND FOUNDATION, WATER DAMAGED INTERIOR FLOORS, WALLS AND CEILINGS (ALL LEVELS). REMODEL OF BASEMENT ENTERTAINMENT AREA, MASTER BATHROOM AND CLOSET. --1 of 3--
- Permit Issued
- Issued on 3/6/2025
- Issuing Office
- Current Status
- Issued on 3/6/2025
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2024 | DAVID CASTILLO |
| Corrections Issued | 12/2/2024 | DAVID CASTILLO |
| Quality Review Completed | 12/2/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/4/2024 | APPLICANT |
| Applicant returned to address corrections | 12/24/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/4/2025 | DAVID CASTILLO |
| Plan Check Approved | 3/6/2025 | DAVID CASTILLO |
| Issued | 3/6/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/23/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 12/24/2024 | DAVID CASTILLO |
| ZA Case | Cleared | 12/26/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | LIAM ODONOVAN |
Contact Information
| Contractor | Gibson Gordon S Inc; Lic. No.: 524012-B | 3000 31ST STREET SUITE G SANTA MONICA, CA 90405 |
| Engineer | Larocca,, Francis; Lic. No.: C75121 | 2008A BELMONT LANE REDONDO BEACH, CA 90278 |
| Engineer | Marte,, Julie Anne; Lic. No.: C84066 | PO BOX 1406 GLENDORA, CA 91740 |
| Engineer | Plouff,, Kacie; Lic. No.: L9013 | 25570 RYE CANYON RD A VALENCIA, CA 91355 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Towers,, Kevin; Lic. No.: S6625 | 6121 IROQUOIS RD WESTMINSTER, CA 92683 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/14/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 5/16/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pool/Spa Cover | 5/16/2025 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/17/2025 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 8/6/2025 | Corrections Issued | DANIEL VERA |
| Shower Pan | 8/8/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/12/2025 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/12/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/18/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/7/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/9/2025 | Partial Approval | SEAN HAUPT |
| Special/Order Compliance | 10/9/2025 | Partial Approval | GEM DE OCAMPO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/6/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/6/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/6/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 11/13/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | CARLOS MATAMOROS |
| Wood Frame | 11/17/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 11/20/2025 | Not Ready for Inspection | DANIEL VERA |
| Drywall Nailing | 12/1/2025 | Approved | SEAN HAUPT |
| Shower Pan | 12/1/2025 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 12/10/2025 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 12/10/2025 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/22/2025 | Approved | CHRISTOPHER WILSON |
| Final | 5/28/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/28/2026 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 5/28/2026 | Not Ready for Inspection | RYAN SALAZAR |