19851 W GRESHAM ST 91324
Certificate Information: 19851 W GRESHAM ST 91324
- Application / Permit
- 24016-30000-36949
- Plan Check / Job No.
- B24WL09128
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BATHROOM REMODEL AND ENCLOSE AREA UNDER PORTION OF (E) ROOF TO CONVERT ONE BATHROOM INTO TWO BATHROOMS PER WFPP
- Permit Issued
- Issued on 12/9/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2024 | RICHARD GARCIA |
| Corrections Issued | 11/19/2024 | RICHARD GARCIA |
| Plan Check Approved | 12/5/2024 | JOHNPAUL ISIP |
| Issued | 12/9/2024 | APPLICANT |
| CofO in Progress | 6/30/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
| CofO Issued | 7/1/2025 | JOHN JANSON |
| Permit Finaled | 7/1/2025 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2024 | Approved | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Rough-Elec/Plmb/HVAC | 1/28/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 2/6/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/10/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 2/18/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 2/21/2025 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/18/2025 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/18/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/18/2025 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 3/18/2025 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 3/18/2025 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/21/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/27/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/27/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/7/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 5/7/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/7/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/7/2025 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/7/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 5/28/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 5/28/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/28/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 6/18/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/18/2025 | Approved | CHRIS CHRISTENSEN |