17219 W RANCHO ST 91316

Certificate Information: 17219 W RANCHO ST 91316

Application / Permit
24016-30000-36911
Plan Check / Job No.
B24WL09110
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Accessory Living Quarter to ADU per 65852.2(e)(1)(A).
Permit Issued
Issued on 12/19/2024
Issuing Office
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2024 APPLICANT
Assigned to Plan Check Engineer 11/20/2024 RICHARD GARCIA
Corrections Issued 11/23/2024 RICHARD GARCIA
Building Plans Picked Up 12/2/2024 APPLICANT
Applicant returned to address corrections 12/12/2024 JAHANSHAH POURHASSAN
Plan Check Approved 12/18/2024 JAHANSHAH POURHASSAN
Issued 12/19/2024 APPLICANT
CofO in Progress 4/8/2026 JON MCHUGH
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/12/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/12/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/12/2024 EDGAR ALCARAZ

Contact Information

Architect Andrews,, John Tiger; Lic. No.: C15605 2109 STONER AVE      LOS ANGELES, CA 90025
Contractor J A G Construction Company Inc; Lic. No.: 806218-B 2109 STONER AVENUE      LOS ANGELES, CA 90025
Engineer Andrada,, Aprile; Lic. No.: C81097 27240 TURNBERRY LANE      VALENCIA, CA 91355
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/24/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 1/24/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 1/24/2025 Not Ready for Inspection JON MCHUGH
Sewer 1/24/2025 Approved JON MCHUGH
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 4/9/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 4/9/2025 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 5/6/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 5/6/2025 Corrections Issued JON MCHUGH
HVAC-Rough 5/6/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 5/6/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 5/22/2025 Not Ready for Inspection JON MCHUGH
HVAC-Rough 5/22/2025 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 5/22/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 7/30/2025 Partial Approval JON MCHUGH
ELECTRICAL-Rough 7/30/2025 Partial Approval JON MCHUGH
HVAC-Rough 7/30/2025 Partial Approval JON MCHUGH
Insulation 8/6/2025 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 8/6/2025 Partial Approval MORRIS JACKSON
Shower Pan 8/6/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/11/2025 Approved JON MCHUGH
Green Building Rough 8/11/2025 Approved JON MCHUGH
Insulation 8/11/2025 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 8/11/2025 Approved JON MCHUGH
Drywall Nailing 8/15/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 3/10/2026 Not Ready for Inspection JON MCHUGH
HVAC-Final 3/10/2026 Not Ready for Inspection JON MCHUGH
PLUMBING-Final 3/10/2026 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 3/19/2026 Approved JON MCHUGH
Final 3/19/2026 Not Ready for Inspection JON MCHUGH
HVAC-Final 3/19/2026 Approved JON MCHUGH
PLUMBING-Final 3/19/2026 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved JON MCHUGH
Smoke Detectors 3/19/2026 Approved JON MCHUGH
Final 4/8/2026 OK to Issue CofO JON MCHUGH