254 N MABERY ROAD 90402
Certificate Information: 254 N MABERY ROAD 90402
- Application / Permit
- 24016-30000-36683
- Plan Check / Job No.
- B24WL09066
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior alterations to a SFD w/ attached garage, remove portion of SFD at the rear
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2024 | KAVIAN REFAHI |
| Corrections Issued | 11/19/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 12/2/2024 | APPLICANT |
| Applicant returned to address corrections | 3/7/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 3/11/2025 | JOHNPAUL ISIP |
| Issued | 3/19/2025 | APPLICANT |
| CofO in Progress | 12/8/2025 | HERBERT GIRON |
| Permit Finaled | 2/2/2026 | RICHARD STEINBACH |
| CofO Issued | 2/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/24/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 12/24/2024 | DIANA RENTERIA |
| ZA Case | Cleared | 12/31/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2025 | DARIN LAM |
| Coastal Zone | Cleared | 2/18/2025 | NATHAN ROMINE |
| Hydrant and Access approval | Cleared | 2/25/2025 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 3/4/2025 | VASIL MIHALEV |
Contact Information
| Contractor | Condev Construction Corp; Lic. No.: 762012-B | 14720 VALERIO STRET VAN NUYS, CA 91405 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/22/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/22/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/22/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/22/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 5/22/2025 | Corrections Issued | HERBERT GIRON |
| Deputy Drilled-In Anchors | 5/23/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 5/23/2025 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 5/30/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 5/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/30/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 6/2/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/2/2025 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 6/2/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 6/6/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | HERBERT GIRON |
| Insulation | 6/12/2025 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 6/26/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 6/26/2025 | Approved | STEPHANIE SWANSON |
| Shower Pan | 6/30/2025 | Approved | HERBERT GIRON |
| Drywall Nailing | 7/7/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/7/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/20/2025 | Corrections Issued | HERBERT GIRON |
| Final | 11/20/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/20/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 11/20/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 11/20/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/4/2025 | Approved | HERBERT GIRON |
| Final | 12/4/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 12/4/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 12/4/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/4/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 12/4/2025 | Approved | HERBERT GIRON |
| Final | 12/8/2025 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 12/8/2025 | Approved | HERBERT GIRON |