3472 S GREENWOOD AVE 90066

Certificate Information: 3472 S GREENWOOD AVE 90066

Application / Permit
24016-30000-36645
Plan Check / Job No.
B24WL09047
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) detached garage to an ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/27/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 REZA HAGHIGHAT
Corrections Issued 11/23/2024 REZA HAGHIGHAT
Quality Review Completed 11/25/2024 KAVIAN REFAHI
Building Plans Picked Up 12/2/2024 APPLICANT
Plan Check Approved 12/27/2024 REZA HAGHIGHAT
Issued 12/27/2024 APPLICANT
CofO in Progress 2/19/2026 DAVID FEILER
Permit Finaled 2/25/2026 RICHARD STEINBACH
CofO Issued 2/25/2026 RICHARD STEINBACH
Permit Finaled 2/25/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/21/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 11/21/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 11/21/2024 KIMBERLY HERNANDEZ
Specific Plan Cleared 12/10/2024 JOSHUA JONES
Grading Pre-Inspection Cleared 12/27/2024 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 2/25/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 3/12/2025 Not Ready for Inspection MICHAEL ALLEN
Footing/Foundation/Slab 3/19/2025 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 3/21/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 7/8/2025 Not Ready for Inspection MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 7/8/2025 Not Ready for Inspection MICHAEL ALLEN
BUILDING-Rough-Frame 7/10/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/24/2025 Approved WILBER ROSALES
HVAC-Final 7/28/2025 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 8/8/2025 Corrections Issued WILBER ROSALES
BUILDING-Rough-Frame 8/14/2025 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Rough 8/14/2025 Approved MICHAEL ALLEN
Green Building Rough 8/14/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 8/14/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 8/14/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 8/14/2025 Corrections Issued MICHAEL ALLEN
Verify Sprinkler Sign Off 8/14/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 8/19/2025 Approved WILBER ROSALES
Green Building Rough 8/19/2025 Approved WILBER ROSALES
HVAC-Rough 8/19/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 8/19/2025 Partial Approval WILBER ROSALES
PLUMBING-Rough 8/19/2025 Approved WILBER ROSALES
Insulation 8/21/2025 Approved WILBER ROSALES
Shower Pan 8/28/2025 Corrections Issued JAYLIN GRAVITTE
Drywall Nailing 8/29/2025 Approved WILBER ROSALES
Shower Pan 9/11/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 9/15/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 1/29/2026 Approved ANTHONY EGSON
Gas Test 1/30/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 1/30/2026 Not Ready for Inspection DANIEL VERA
Final 2/3/2026 Corrections Issued MICHAEL ALLEN
Green Building Final 2/3/2026 Approved MICHAEL ALLEN
HVAC-Final 2/3/2026 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 2/3/2026 Approved MICHAEL ALLEN
Gas Test 2/13/2026 Approved ANTHONY EGSON
HVAC-Final 2/13/2026 Approved ANTHONY EGSON
PLUMBING-Final 2/13/2026 Approved ANTHONY EGSON
Final 2/19/2026 OK to Issue CofO DAVID FEILER