1915 S PENMAR AVE 90291
Certificate Information: 1915 S PENMAR AVE 90291
- Application / Permit
- 24016-30000-35402
- Plan Check / Job No.
- B24WL08693
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- INTERIOR AND EXTERIOR REMODEL AND TENANT IMPROVEMENT TO (E) RETAIL
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/2/2026
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Zoning Architect | 11/7/2024 | MELISSA QUINONES |
| Assigned to Plan Check Engineer | 11/14/2024 | DANIEL YIP |
| Corrections Issued | 11/22/2024 | DANIEL YIP |
| Quality Review Completed | 12/6/2024 | KEN GILL |
| Building Plans Picked Up | 12/12/2024 | APPLICANT |
| Green Plans Picked Up | 12/12/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 1/22/2025 | APPLICANT |
| Plan Check Approved | 1/23/2025 | DANIEL YIP |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 5/12/2026 | FARHAD DADBIN |
| Permit Finaled | 6/2/2026 | VASIL MIHALEV |
| CofO in Progress | 6/2/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Green Code | Cleared | 1/17/2025 | MICHAEL AYERS |
| "Q" conditions | Cleared | 1/23/2025 | DANIEL CORONADO |
| DAS Clearance | Cleared | 1/23/2025 | DANIEL YIP |
| Zoning Plan Check | Cleared | 1/23/2025 | MELISSA QUINONES |
Contact Information
| Contractor | Right Image Builders Inc; Lic. No.: 1021284-B | 5437 LAUREL CANUON BLVD #108 VALLEY VILLAGE, CA 91607 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2025 | Corrections Issued | FARHAD DADBIN |
| Pre-Inspection | 2/19/2025 | Corrections Issued | FARHAD DADBIN |
| Wood Frame | 3/25/2025 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 4/14/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 6/10/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 6/16/2025 | Corrections Issued | FARHAD DADBIN |
| Wood Frame | 6/17/2025 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 8/5/2025 | Conditional Approval | FARHAD DADBIN |
| Insulation | 9/29/2025 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 10/22/2025 | Approved | VASIL MIHALEV |
| Drywall Nailing | 10/23/2025 | Conditional Approval | FARHAD DADBIN |
| Pre-Inspection | 1/29/2026 | Corrections Issued | FARHAD DADBIN |
| Final | 5/8/2026 | Partial Approval | FARHAD DADBIN |
| Green Building Final | 5/8/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 5/8/2026 | Approved | FARHAD DADBIN |
| Final | 5/12/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 6/2/2026 | Permit Finaled | VASIL MIHALEV |