6619 W 5TH ST 90048
Certificate Information: 6619 W 5TH ST 90048
- Application / Permit
- 24016-30000-35353
- Plan Check / Job No.
- B24WL08681
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 3/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2024 | RICHARD GARCIA |
| Corrections Issued | 11/6/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 11/15/2024 | APPLICANT |
| Plan Check Approved | 2/13/2025 | JOHNPAUL ISIP |
| Issued | 3/7/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/21/2025 | RIDWAN HARDY |
| Address approval | Cleared | 2/1/2025 | PAMELA TENEZA |
| Roof/Waste drainage to street | Cleared | 2/1/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 2/1/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | PAMELA TENEZA |
Contact Information
| Contractor | Lonestar West Construction; Lic. No.: 768001-B | 3656 MC LAUGHLIN AVENUE LOS ANGELES, CA 90066 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/2/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/8/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/8/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/15/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/21/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/9/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 7/9/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/9/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/30/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 7/30/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/11/2025 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 8/11/2025 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 9/5/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/5/2025 | Partial Approval | EVAN COOPER |
| Shower Pan | 9/26/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/6/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 10/15/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 4/21/2026 | Corrections Issued | WILBER ROSALES |
| Final | 4/21/2026 | Partial Approval | WILBER ROSALES |
| Green Building Final | 4/21/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 4/21/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 4/21/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 4/21/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 4/21/2026 | Approved | WILBER ROSALES |