2205 N CANYONBACK ROAD 90049

Certificate Information: 2205 N CANYONBACK ROAD 90049

Application / Permit
24016-30000-32543
Plan Check / Job No.
B24WL07968
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
Convert 130 sf of attached garage to habitable space and close 83 sf opening between 1st & 2nd floors. No changes to the footprint of building or site plan.
Permit Issued
Issued on 11/21/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 JAHANSHAH POURHASSAN
Corrections Issued 10/15/2024 JAHANSHAH POURHASSAN
Building Plans Picked Up 10/16/2024 APPLICANT
Applicant returned to address corrections 11/5/2024 CAROLEAN BASMA
Plan Check Approved 11/19/2024 DAVID CASTILLO
Issued 11/21/2024 APPLICANT
CofO in Progress 11/21/2025 CASIMIR BRITTON
Permit Finaled 11/26/2025 DAVID TSAU
CofO Issued 11/26/2025 DAVID TSAU
Permit Finaled 11/26/2025 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 10/28/2024 DAVID URITA
ZA Case Cleared 10/28/2024 DAVID URITA
ZA Case Cleared 10/28/2024 DAVID URITA
ZA Case Cleared 10/28/2024 DAVID URITA
Grading Pre-Inspection Cleared 10/28/2024 VASIL MIHALEV

Contact Information

Contractor Delta West Construction; Lic. No.: 794816-B 132 S LA PEER DR      BEVERLY HILLS, CA 90211
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2024 Conditional Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 1/31/2025 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 2/12/2025 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 2/26/2025 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 3/6/2025 Conditional Approval GRANT WOODS
FLOOD-Proofing Certificate 3/12/2025 Approved PAUL DAVIDSON
Green Building Rough 3/12/2025 Approved PAUL DAVIDSON
Wood Frame 3/12/2025 Approved PAUL DAVIDSON
Insulation 3/14/2025 Approved PAUL DAVIDSON
Drywall Nailing 3/20/2025 Partial Approval GRANT WOODS
Drywall Nailing 4/1/2025 Partial Approval CASIMIR BRITTON
Pre-Inspection 4/10/2025 Partial Inspection CASIMIR BRITTON
Interior/Exterior Lathing 4/22/2025 Approved CASIMIR BRITTON
Drywall Nailing 9/9/2025 Not Ready for Inspection CASIMIR BRITTON
Final 9/9/2025 Corrections Issued CASIMIR BRITTON
Footing/Foundation/Slab 9/9/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 9/9/2025 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 9/9/2025 Not Ready for Inspection CASIMIR BRITTON
Drywall Nailing 10/15/2025 Not Ready for Inspection CASIMIR BRITTON
Final 10/15/2025 Not Ready for Inspection CASIMIR BRITTON
Footing/Foundation/Slab 10/15/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 10/15/2025 Not Ready for Inspection CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 10/15/2025 Not Ready for Inspection CASIMIR BRITTON
Drywall Nailing 11/3/2025 Approved CASIMIR BRITTON
Final 11/3/2025 Not Ready for Inspection CASIMIR BRITTON
Footing/Foundation/Slab 11/3/2025 Approved CASIMIR BRITTON
Green Building Final 11/3/2025 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 11/3/2025 Approved CASIMIR BRITTON
Final 11/21/2025 OK to Issue CofO CASIMIR BRITTON