2352 S MIDVALE AVE 90064
Certificate Information: 2352 S MIDVALE AVE 90064
- Application / Permit
- 24016-30000-27448
- Plan Check / Job No.
- B24WL06574
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) RECREATION ROOM (PERMIT# 06010-30000-04829) ABOVE THE (E) 2 CAR GARAGE INTO A N ADU PER CA GOVT. CODE 65852.2(E)(1)(A).
- Permit Issued
- Issued on 1/21/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2024 | RICHARD GARCIA |
| Corrections Issued | 8/28/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 8/30/2024 | APPLICANT |
| Plan Check Approved | 1/16/2025 | RICHARD GARCIA |
| Issued | 1/21/2025 | APPLICANT |
| CofO in Progress | 3/6/2025 | RUBEN PEREZ |
| Permit Finaled | 3/13/2025 | DANIEL SANCHEZ |
| CofO Issued | 3/13/2025 | DANIEL SANCHEZ |
| Permit Finaled | 3/13/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2024 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/16/2024 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 10/22/2024 | JULISSA LOPEZ-HODOYAN |
| Construction near power lines | Cleared | 12/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/29/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 1/29/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 1/29/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Pre-Inspection | 2/6/2025 | Approved | PETER RUBIO |
| Rough-Elec/Plmb/HVAC | 2/19/2025 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | PETER RUBIO |
| Final | 2/25/2025 | OK to Issue CofO | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | PETER RUBIO |
| Smoke Detectors | 2/25/2025 | Approved | PETER RUBIO |