10540 W ALMAYO AVE 90064
Certificate Information: 10540 W ALMAYO AVE 90064
- Application / Permit
- 24016-30000-22552
- Plan Check / Job No.
- B24WL01509
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2024 | JOHNPAUL ISIP |
| Corrections Issued | 7/17/2024 | JOHNPAUL ISIP |
| Building Plans Picked Up | 7/23/2024 | APPLICANT |
| Applicant returned to address corrections | 9/27/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 10/8/2024 | ALFREDO JARA |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | DANIEL VERA |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
| CofO Issued | 4/24/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | DARIN LAM |
| Sewer availability | Cleared | 8/6/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 8/8/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 8/12/2024 | HAMID GHAEMMAGHAMI |
| Roof/Waste drainage to street | Cleared | 10/1/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Dirty Girl Construction Inc; Lic. No.: 934287-B | 4321 STEWART AVENUE LOS ANGELES, CA 90066 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2024 | Partial Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 11/13/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/13/2024 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/15/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Barrier | 11/15/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/7/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 1/7/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 1/7/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/7/2025 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 1/7/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2025 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/9/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/30/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 1/30/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/30/2025 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 2/3/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/4/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/18/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/10/2025 | Approved | DANIEL VERA |
| Final | 4/10/2025 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 4/10/2025 | Approved | DANIEL VERA |
| HVAC-Final | 4/10/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 4/10/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Required | DANIEL VERA |
| Service/Power Release | 4/10/2025 | Approved | DANIEL VERA |
| Smoke Detectors | 4/10/2025 | Approved | DANIEL VERA |