7701 S HOSFORD AVE 90045
Certificate Information: 7701 S HOSFORD AVE 90045
- Application / Permit
- 24016-30000-22275
- Plan Check / Job No.
- B24WL01487
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior structural remodel with a small addition to an existing S.F.R and new uncovered deck in the rear
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | RICHARD GARCIA |
| Corrections Issued | 7/14/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 7/15/2024 | APPLICANT |
| Applicant returned to address corrections | 8/1/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 8/9/2024 | AMY GUEVARRA |
| Plan Check Approved | 8/12/2024 | AMY GUEVARRA |
| Issued | 8/16/2024 | APPLICANT |
| CofO in Progress | 8/1/2025 | RUBEN RIVAS |
| Permit Finaled | 8/16/2025 | RICHARD STEINBACH |
| CofO Issued | 8/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/30/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 7/30/2024 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 7/31/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 8/9/2024 | RICHARD GARCIA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Zepeda Juan; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 9/17/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/10/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 12/2/2024 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 12/2/2024 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/9/2024 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Rough | 12/9/2024 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/9/2024 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 1/28/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 1/28/2025 | Conditional Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/4/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/4/2025 | Partial Approval | MICHAEL ALLEN |
| METHANE-Rough | 2/4/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/6/2025 | No Access for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/6/2025 | No Access for Inspection | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 2/12/2025 | Approved | MICHAEL ALLEN |
| Insulation | 2/12/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | MICHAEL ALLEN |
| Insulation | 2/18/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 2/25/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Drywall Nailing | 2/27/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 3/10/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/10/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/20/2025 | Approved | JAYLIN GRAVITTE |
| Gas Test | 6/18/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 7/15/2025 | Approved | RUBEN RIVAS |
| Final | 7/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 7/16/2025 | Approved | ANTHONY EGSON |
| Final | 7/21/2025 | No Access for Inspection | RUBEN RIVAS |
| Final | 7/28/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 7/31/2025 | OK to Issue CofO | RUBEN RIVAS |