2803-2805 S MEDILL PL 90064

Certificate Information: 2803-2805 S MEDILL PL 90064

Application / Permit
24016-30000-22251
Plan Check / Job No.
B24WL01481
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) Attached Garage to (E) SFD conversion to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 10/9/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/12/2024 RICHARD GARCIA
Corrections Issued 7/14/2024 RICHARD GARCIA
Building Plans Picked Up 7/16/2024 APPLICANT
Applicant returned to address corrections 8/1/2024 CAROLEAN BASMA
Plan Check Approved 8/12/2024 EDWIN ESPIN
Issued 10/9/2024 APPLICANT
CofO in Progress 5/9/2025 MEL KHACHATOURIAN
Permit Finaled 5/9/2025 RICHARD STEINBACH
CofO Issued 5/9/2025 RICHARD STEINBACH
Permit Finaled 5/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/17/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 7/17/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/18/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 7/23/2024 VASIL MIHALEV
Specific Plan Cleared 8/6/2024 HAMID GHAEMMAGHAMI
ZA Case Cleared 8/6/2024 DALIA MOKAYED

Contact Information

Contractor Rockridge Construction Co; Lic. No.: 1053981-B 485 S ROBERTSON BLVD #5      BEVERLY HILLS, CA 90211
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 11/6/2024 Corrections Issued ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 11/8/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 11/8/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 1/24/2025 Corrections Issued ARAM AVEDISIAN
Green Building Rough 1/24/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 1/24/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 1/24/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/30/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 1/30/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Approved ARAM AVEDISIAN
Green Building Rough 1/30/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 1/30/2025 Approved ARAM AVEDISIAN
Insulation 1/30/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 3/4/2025 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 3/17/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 3/28/2025 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/8/2025 Approved MEL KHACHATOURIAN
Drywall Nailing 5/8/2025 Approved MEL KHACHATOURIAN
Final 5/8/2025 OK to Issue CofO MEL KHACHATOURIAN
Green Building Final 5/8/2025 Approved MEL KHACHATOURIAN
Green Building Rough 5/8/2025 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV No Gas MEL KHACHATOURIAN
Smoke Detectors 5/8/2025 Approved MEL KHACHATOURIAN