7902 S COWAN AVE 90045

Certificate Information: 7902 S COWAN AVE 90045

Application / Permit
24016-30000-21868
Plan Check / Job No.
B24WL01450
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to ADU per CA Gov't Code 65852.2(e)(1)(A).
Permit Issued
Issued on 1/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 DAVID CASTILLO
Corrections Issued 7/15/2024 DAVID CASTILLO
Building Plans Picked Up 7/15/2024 APPLICANT
Applicant returned to address corrections 11/14/2024 CAROLEAN BASMA
Plan Check Approved 12/17/2024 RICHARD GARCIA
Issued 1/15/2025 APPLICANT
CofO in Progress 3/9/2026 DAVID FEILER
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 11/3/2024 TINA MIRANDA
Address approval Cleared 11/4/2024 DARIN LAM
Roof/Waste drainage to street Cleared 11/4/2024 DARIN LAM
Sewer availability Cleared 11/4/2024 DARIN LAM
Grading Pre-Inspection Cleared 11/4/2024 VASIL MIHALEV
Specific Plan Cleared 11/5/2024 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 11/13/2024 DARIN LAM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B 8125 LOYOLA BLVD      LOS ANGELES, CA 90045

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/16/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 4/15/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 9/18/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 9/18/2025 Partial Approval RUBEN RIVAS
Green Building Rough 9/18/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 9/18/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 9/18/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 10/10/2025 Corrections Issued RUBEN RIVAS
HVAC-Rough 10/10/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 10/10/2025 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 10/14/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 10/14/2025 Corrections Issued RUBEN RIVAS
Green Building Rough 10/14/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 10/14/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 10/14/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 10/22/2025 Partial Approval RUBEN RIVAS
Green Building Rough 10/22/2025 Not Ready for Inspection RUBEN RIVAS
Insulation 10/31/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 10/31/2025 Partial Approval RUBEN RIVAS
Drywall Nailing 11/5/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 1/14/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 1/14/2026 Not Ready for Inspection ANTHONY EGSON
Final 1/14/2026 Corrections Issued ANTHONY EGSON
Green Building Final 1/14/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 1/14/2026 Approved ANTHONY EGSON
HVAC-Final 1/14/2026 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/14/2026 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 1/14/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 2/25/2026 Approved ANTHONY EGSON
Final 2/25/2026 OK to Issue CofO ANTHONY EGSON
Green Building Final 2/25/2026 Approved ANTHONY EGSON
HVAC-Final 2/25/2026 Approved ANTHONY EGSON
PLUMBING-Final 2/25/2026 Approved ANTHONY EGSON
Service/Power Release 2/25/2026 Approved ANTHONY EGSON
Smoke Detectors 2/25/2026 Approved ANTHONY EGSON