3601-3603 N VERDUGO ROAD 90065

Certificate Information: 3601-3603 N VERDUGO ROAD 90065

Application / Permit
24016-30000-21577
Plan Check / Job No.
X24WL04860
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(2) Kitchen and (2) Bathroom remodel for residential buildings (no structural changes) INCLUDING MEPS(ELECTRICAL, PLUMBING & HVAC), Re-stucco for residential buildings. ,Replace drywall (no new walls added) for single family dwellings and duplexes only., (9)Window and (8) door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2(b) 1B of Title 24. & Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing __20____Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b) 2B. "COMPLY WITH DEPARTMENT ORDER effective date 07/03/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/5/2024
Issuing Office
West Los Angeles
Current Status
Issued on 7/5/2024

Permit Application Status History

Issued 7/5/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Alloy Construction And Restoration; Lic. No.: 1054043-B 813 DEERFLATS DR      SAN DIMAS, CA 91773

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/14/2024 Corrections Issued FERMIN RUBIO
ELECTRICAL-Rough 11/14/2024 Not Ready for Inspection FERMIN RUBIO
Special/Order Compliance 12/3/2024 Corrections Issued JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Corrections Issued ROBERT MINASSIANS
BUILDING-Rough-Frame 5/8/2025 Approved FERMIN RUBIO
Drywall Nailing 5/8/2025 Partial Approval FERMIN RUBIO
ELECTRICAL-Rough 5/8/2025 Approved FERMIN RUBIO
Insulation 5/8/2025 Approved FERMIN RUBIO
MERV13>=Rough 5/8/2025 Approved FERMIN RUBIO
PLUMBING-Rough 5/8/2025 Approved FERMIN RUBIO
Drywall Nailing 5/14/2025 Conditional Approval FERMIN RUBIO
Final 8/21/2025 Corrections Issued FERMIN RUBIO
MERV13>=Final 8/21/2025 Not Ready for Inspection FERMIN RUBIO
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved FERMIN RUBIO
Smoke Detectors 8/21/2025 Corrections Issued FERMIN RUBIO
Drywall Nailing 10/3/2025 Approved FERMIN RUBIO
ELECTRICAL-Final 2/12/2026 Corrections Issued FERMIN RUBIO