110 N ROCKINGHAM AVE 90049
Certificate Information: 110 N ROCKINGHAM AVE 90049
- Application / Permit
- 24016-30000-19983
- Plan Check / Job No.
- B24WL01321
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- convert attached 3-car garage into den and bedroom w/ foundation under pinning *** 2 of 2 ***
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | KAVIAN REFAHI |
| Corrections Issued | 6/23/2024 | KAVIAN REFAHI |
| Quality Review Completed | 6/26/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 6/28/2024 | APPLICANT |
| Plan Check Approved | 9/23/2024 | KAVIAN REFAHI |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 9/17/2025 | KEVIN SARGSYAN |
| Permit Finaled | 12/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/3/2025 | RICHARD STEINBACH |
| CofO Issued | 12/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 7/22/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 9/23/2024 | KAVIAN REFAHI |
Contact Information
| Architect | Brunn,, Dan; Lic. No.: C31368 | 737 S LONGWOOD AVENUE LOS ANGELES, CA 90005 |
| Contractor | Owner-Builder | , |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 27240 TURNBERRY LN STE 200 VALENCIA, CA 91355 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 10/21/2024 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/5/2024 | Partial Approval | ARAM AVEDISIAN |
| Underground Mechanical | 11/7/2024 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 11/13/2024 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 11/18/2024 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 12/6/2024 | Partial Approval | KENNETH NAGLE |
| Underground Mechanical | 12/9/2024 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/19/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 12/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/6/2025 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 1/22/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/22/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 2/24/2025 | Approved | REGINA MENDEZ |
| Insulation | 2/25/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/3/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/20/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 8/26/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 8/26/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/3/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 9/3/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | KEVIN SARGSYAN |
| Final | 9/17/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| HVAC-Final | 9/17/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 9/17/2025 | Approved | KEVIN SARGSYAN |