5333 S MCCONNELL AVE 90066
Certificate Information: 5333 S MCCONNELL AVE 90066
- Application / Permit
- 24016-30000-17623
- Plan Check / Job No.
- B24WL01170
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- first interior tenant improvment/alteration on the 1st and mezzanine floor of an existing 47,257 sf industrial buiding to include demolition of existing interior non-bearing partitions, doors, ceiling and finishes. remodel existing office space with new ceiling, floor & wall finishes, new accessible single and multi-user restrooms in office and warehouse.
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Zoning Architect | 5/30/2024 | CALEB WONG |
| Assigned to Plan Check Engineer | 6/6/2024 | KAVIAN REFAHI |
| Green Plans Picked Up | 6/7/2024 | APPLICANT |
| Corrections Issued | 6/9/2024 | KAVIAN REFAHI |
| Disabled Access Plans Picked Up | 6/10/2024 | APPLICANT |
| Quality Review Completed | 6/26/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 6/27/2024 | APPLICANT |
| Plan Check Approved | 9/6/2024 | KAVIAN REFAHI |
| Issued | 9/16/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 7/9/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 7/16/2024 | SHINE LIN |
| Zoning Plan Check | Cleared | 7/22/2024 | CALEB WONG |
Contact Information
| Architect | Kellogg,, Mark Robert; Lic. No.: C22989 | 29619 AGOURA ROAD AGOURA HILLS, CA 91301 |
| Contractor | R C I Builders Inc; Lic. No.: 835114-B | 2985 E HILLCREST DR #107 THOUSAND OAKS, CA 91362 |
| Engineer | Lubberts,, Jeffrey Scott; Lic. No.: S6432 | 1548 KIRK AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 10/15/2024 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/16/2024 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 11/15/2024 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Approved | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 11/26/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Drywall Nailing | 12/16/2024 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 12/20/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 12/27/2024 | Partial Approval | RICARDO ROBLES |
| Footing/Foundation/Slab | 12/27/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 12/27/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 12/27/2024 | Partial Approval | RICARDO ROBLES |
| Deputy Wood Construction | 12/31/2024 | Approved | GRANT WOODS |
| Insulation | 12/31/2024 | Partial Approval | GRANT WOODS |
| Wood Frame | 12/31/2024 | Corrections Issued | GRANT WOODS |
| Drywall Nailing | 1/6/2025 | Partial Approval | RICARDO ROBLES |
| Footing/Foundation/Slab | 1/6/2025 | Partial Approval | RICARDO ROBLES |
| Insulation | 1/6/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 1/6/2025 | Partial Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 1/7/2025 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 1/7/2025 | Partial Approval | RICARDO ROBLES |
| Insulation | 1/7/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Reinforced Concrete Frame | 1/9/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 2/21/2025 | Not Ready for Inspection | AMANUEL BERHE |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Partial Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 2/21/2025 | Partial Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 2/21/2025 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 3/12/2025 | Corrections Issued | GRANT WOODS |
| Green Building Final | 3/12/2025 | Not Ready for Inspection | GRANT WOODS |
| Green Building Rough | 3/12/2025 | Approved | GRANT WOODS |
| METHANE-Final | 3/12/2025 | Approved | GRANT WOODS |
| METHANE-Rough | 3/12/2025 | Approved | GRANT WOODS |
| Reinforced Masonry Frame | 3/12/2025 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/12/2025 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 3/12/2025 | Not Ready for Inspection | GRANT WOODS |
| T-Bar Ceiling | 3/12/2025 | Not Ready for Inspection | GRANT WOODS |
| Final | 3/19/2025 | Partial Inspection | GRANT WOODS |
| Green Building Final | 3/19/2025 | Not Ready for Inspection | GRANT WOODS |
| Reinforced Masonry Frame | 3/19/2025 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 3/19/2025 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 4/15/2026 | Conditional Approval | DANIEL ARMENTA |