336 N ARDEN BLVD 90004
Certificate Information: 336 N ARDEN BLVD 90004
- Application / Permit
- 24016-30000-16177
- Plan Check / Job No.
- B24WL01057
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior and exterior structural remodel to an existing 1-story S.F.R. scope of work to include: new concrete outdoor porch in the rear
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/21/2025
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | ZENA HADDIS |
| Corrections Issued | 5/17/2024 | ZENA HADDIS |
| Building Plans Picked Up | 5/21/2024 | APPLICANT |
| Plan Check Approved | 6/5/2024 | AMY GUEVARRA |
| Issued | 6/7/2024 | APPLICANT |
| Permit Finaled | 3/20/2025 | JEFFREY MEAD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Vip Construction 1 Inc; Lic. No.: 1097925-B | 11038 BENWELL DRIVE APT D LYNWOOD, CA 90262 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/24/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/9/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/9/2024 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 8/9/2024 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 9/4/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/3/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/3/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/3/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 10/3/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 10/11/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/11/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/21/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/5/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 2/6/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/6/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 2/12/2025 | Approved | JEFFREY MEAD |
| HVAC-Final | 2/12/2025 | Approved | JEFFREY MEAD |
| Final | 3/14/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 3/14/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 3/14/2025 | Approved | BRENDAN MORELLI |
| Final | 3/20/2025 | Permit Finaled | JEFFREY MEAD |