2121 S LINCOLN BLVD 90291

Certificate Information: 2121 S LINCOLN BLVD 90291

Application / Permit
24016-30000-16084
Plan Check / Job No.
B24WL01045
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
re-stripe parking lot
Permit Issued
Issued on 2/12/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 KAVIAN REFAHI
Corrections Issued 5/27/2024 KAVIAN REFAHI
Quality Review Completed 5/30/2024 CHIHARU SUZUKI
Building Plans Picked Up 5/31/2024 APPLICANT
Disabled Access Plans Picked Up 6/10/2024 APPLICANT
Applicant returned to address corrections 1/15/2025 KAVIAN REFAHI
Plan Check Approved 2/12/2025 KAVIAN REFAHI
Issued 2/12/2025 APPLICANT
CofO in Progress 5/23/2025 FARHAD DADBIN
Permit Finaled 5/29/2025 DAVID TSAU
CofO Issued 5/29/2025 DAVID TSAU
Permit Finaled 5/29/2025 DAVID TSAU

Permit Application Clearance Information

Coastal Zone Cleared 7/2/2024 BRENNEN OBETO
Miscellaneous Cleared 7/2/2024 BRENNEN OBETO
ZA Case Cleared 7/2/2024 BRENNEN OBETO
ZA Case Cleared 7/2/2024 BRENNEN OBETO
ZA Case Cleared 7/2/2024 BRENNEN OBETO
DAS Clearance Cleared 7/16/2024 KAVIAN REFAHI
Specific Plan Cleared 10/22/2024 FREDDY GARCIA
"Q" conditions Cleared 12/11/2024 LUIS LOPEZ
Specific Plan Cleared 12/11/2024 LUIS LOPEZ
Supp. Use District POD/CDO/TDO Cleared 12/11/2024 LUIS LOPEZ
Prkng lot landscape/Water mgmt Cleared 12/19/2024 BRENNEN OBETO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Ag Home Solutions Inc; Lic. No.: 1047430-B 8030 REMMET AVE STE 1      CANOGA PARK, CA 91304

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/2/2025 Not Ready for Inspection VASIL MIHALEV
Final 4/4/2025 Corrections Issued VASIL MIHALEV
Wood Frame 4/4/2025 Not Ready for Inspection VASIL MIHALEV
Final 5/6/2025 Not Ready for Inspection FARHAD DADBIN
Wood Frame 5/6/2025 Approved FARHAD DADBIN
Final 5/21/2025 OK to Issue CofO FARHAD DADBIN