12522 W RUBENS AVE 90066

Certificate Information: 12522 W RUBENS AVE 90066

Application / Permit
24016-30000-15544
Plan Check / Job No.
B24WL01009
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) detached garage and storage room to an ADU (480 sf) per PER GCS 65852.2(e)(1)(A). All work per WFPP.
Permit Issued
Issued on 10/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 REZA HAGHIGHAT
Corrections Issued 5/14/2024 REZA HAGHIGHAT
Building Plans Picked Up 5/15/2024 APPLICANT
Applicant returned to address corrections 10/1/2024 AMY GUEVARRA
Plan Check Approved 10/2/2024 REZA HAGHIGHAT
Issued 10/4/2024 APPLICANT
CofO Issued 2/1/2025 RICHARD STEINBACH
Permit Finaled 2/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/21/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/21/2024 DARIN LAM
Sewer availability Cleared 5/21/2024 DARIN LAM
Specific Plan Cleared 6/4/2024 RICHARD WOO
Construction near power lines Cleared 9/10/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/27/2024 Approved MICHAEL ALLEN
Footing/Foundation/Slab 11/27/2024 Approved MICHAEL ALLEN
HVAC-Rough 11/27/2024 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 11/27/2024 Approved MICHAEL ALLEN
Wood Frame 12/4/2024 Approved MICHAEL ALLEN
ELECTRICAL-Rough 12/9/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/9/2024 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 12/12/2024 Conditional Approval MICHAEL ALLEN
Interior/Exterior Lathing 12/12/2024 Partial Approval MICHAEL ALLEN
Insulation 12/13/2024 Approved MICHAEL ALLEN
Drywall Nailing 12/17/2024 Approved JESUS PINEDA
Green Building Rough 12/17/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 12/17/2024 Approved JESUS PINEDA
Shower Pan 12/17/2024 Approved JESUS PINEDA
ELECTRICAL-Final 12/31/2024 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/7/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 1/7/2025 Approved MICHAEL ALLEN
Final 1/7/2025 Corrections Issued MICHAEL ALLEN
Gas Test 1/7/2025 Approved MICHAEL ALLEN
Green Building Final 1/7/2025 Approved MICHAEL ALLEN
HVAC-Final 1/7/2025 Approved MICHAEL ALLEN
PLUMBING-Final 1/7/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 1/7/2025 Approved MICHAEL ALLEN
Final 1/14/2025 Partial Approval MICHAEL ALLEN