5755-5757 W 74TH ST 90045
Certificate Information: 5755-5757 W 74TH ST 90045
- Application / Permit
- 24016-30000-15012
- Plan Check / Job No.
- B24WL00965
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) attached garage to a JADU (400 sf) per GCS 65852.2(e)(1)(A) AND 65852.22 in (E) single story SFD ; all work per WFPP
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | ZENA HADDIS |
| Corrections Issued | 5/8/2024 | ZENA HADDIS |
| Building Plans Picked Up | 5/14/2024 | APPLICANT |
| Applicant returned to address corrections | 5/24/2024 | AMY GUEVARRA |
| Issued | 6/14/2024 | APPLICANT |
| CofO in Progress | 8/27/2024 | BOBBY KEY |
| Permit Finaled | 8/27/2024 | RICHARD STEINBACH |
| CofO Issued | 8/27/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/27/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2024 | DARIN LAM |
| Sewer availability | Cleared | 5/22/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2024 | DARIN LAM |
| ZA Case | Cleared | 5/23/2024 | DANIEL CORONADO |
| Specific Plan | Cleared | 6/13/2024 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/3/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 7/3/2024 | Partial Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 7/3/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 7/3/2024 | Corrections Issued | JESUS PINEDA |
| MERV13>=Rough | 7/3/2024 | Not Ready for Inspection | JESUS PINEDA |
| Deputy Drilled-In Anchors | 7/15/2024 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/17/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/17/2024 | Approved | BOBBY KEY |
| Green Building Rough | 7/17/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | BOBBY KEY |
| MERV13>=Rough | 7/17/2024 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 7/17/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 7/17/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | BOBBY KEY |
| Green Building Rough | 7/23/2024 | Approved | BOBBY KEY |
| HVAC-Final | 7/23/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 7/23/2024 | Approved | BOBBY KEY |
| Insulation | 7/23/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 7/30/2024 | Approved | RICHARD STEINBACH |
| HVAC-Final | 7/30/2024 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 7/30/2024 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 8/1/2024 | Approved | BOBBY KEY |
| Sewer | 8/15/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/23/2024 | Approved | BOBBY KEY |
| Final | 8/23/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/23/2024 | Approved | BOBBY KEY |
| HVAC-Final | 8/23/2024 | Approved | BOBBY KEY |
| MERV13>=Final | 8/23/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/23/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/23/2024 | Approved | BOBBY KEY |
| Final | 8/27/2024 | OK to Issue CofO | BOBBY KEY |