2809 W ANGUS ST 90039
Certificate Information: 2809 W ANGUS ST 90039
- Application / Permit
- 24016-30000-14865
- Plan Check / Job No.
- B24WL00946
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EXISTING 3 GARAGE AND STORAGE ROOM INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A) PER WFPP
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | RICHARD GARCIA |
| Corrections Issued | 5/8/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 5/13/2024 | APPLICANT |
| Applicant returned to address corrections | 10/7/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 10/15/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 11/4/2024 | DAVID CASTILLO |
| Issued | 11/4/2024 | APPLICANT |
| No Progress | 5/8/2025 | DEROLD HAUFF |
| CofO in Progress | 5/8/2025 | DEROLD HAUFF |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
| Permit Finaled | 5/15/2025 | DEROLD HAUFF |
| CofO Issued | 5/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 7/30/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2024 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 10/7/2024 | AMY GUEVARRA |
| Tenant Habitability Plan | Cleared | 11/4/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/22/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/22/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/27/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/3/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/11/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/24/2024 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/7/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/7/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 1/13/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 1/13/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/21/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/21/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 1/27/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/27/2025 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 1/31/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/31/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/11/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/9/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/9/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/9/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 4/9/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/9/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/9/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 4/14/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 4/14/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/14/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/21/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 4/21/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/21/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/22/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/22/2025 | Conditional Approval | ENRIQUE MIRELES |
| HVAC-Final | 4/22/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/22/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/24/2025 | Corrections Issued | ENRIQUE MIRELES |