711 S WESTGATE AVE 90049

Certificate Information: 711 S WESTGATE AVE 90049

Application / Permit
24016-30000-12833
Plan Check / Job No.
B24WL00816
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remoel of (e) SFD & convert attached garage into JADU per CA G.C. 65852.2(e)(1)(A) & 65852.22. Add (n) uncovered wood deck to the rear of the SFD.
Permit Issued
Issued on 5/10/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/19/2024 JAHANSHAH POURHASSAN
Corrections Issued 4/22/2024 JAHANSHAH POURHASSAN
Building Plans Picked Up 4/22/2024 APPLICANT
Plan Check Approved 5/9/2024 ALFREDO JARA
Issued 5/10/2024 APPLICANT
CofO in Progress 11/1/2024 JESUS RODRIGUEZ
Permit Finaled 11/5/2024 RICHARD STEINBACH
CofO Issued 11/5/2024 RICHARD STEINBACH
Permit Finaled 11/5/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/9/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/9/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/9/2024 JAHANSHAH POURHASSAN
Sewer availability Cleared 5/9/2024 ANTHONY MAINEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Vip Construction 1 Inc; Lic. No.: 1097925-B 11038 BENWELL DRIVE APT D      LYNWOOD, CA 90262
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/4/2024 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 6/10/2024 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 6/13/2024 Partial Approval MICHAEL PELHAM
ELECTRICAL-Rough 7/18/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 7/18/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/7/2024 Approved ARAM AVEDISIAN
Sewer 8/7/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/9/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/12/2024 Approved ARAM AVEDISIAN
Deputy Wood Construction 8/12/2024 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 8/12/2024 Partial Approval ARAM AVEDISIAN
Insulation 8/15/2024 Corrections Issued KEVIN SARGSYAN
Insulation 8/19/2024 Approved ARAM AVEDISIAN
Drywall Nailing 8/22/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 8/22/2024 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 8/26/2024 Approved JESUS RODRIGUEZ
Shower Pan 8/26/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/29/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/25/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Final 10/25/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 10/25/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 10/25/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Not Ready SEAN HAUPT
Final 10/30/2024 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 10/30/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 11/1/2024 Approved JESUS RODRIGUEZ
Final 11/1/2024 OK to Issue CofO JESUS RODRIGUEZ
Gas Test 11/1/2024 Approved JESUS RODRIGUEZ
HVAC-Final 11/1/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/1/2024 Approved JESUS RODRIGUEZ