2267 S PELHAM AVE 90064
Certificate Information: 2267 S PELHAM AVE 90064
- Application / Permit
- 24016-30000-11508
- Plan Check / Job No.
- B24WL00742
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2 CAR GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 3/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2024 | JASON JANGADA |
| Corrections Issued | 4/13/2024 | JASON JANGADA |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Applicant returned to address corrections | 11/18/2024 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 12/3/2024 | JOHNPAUL ISIP |
| Issued | 3/21/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/4/2024 | VASIL MIHALEV |
| Address approval | Cleared | 6/12/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 6/12/2024 | DIANA RENTERIA |
| Specific Plan | Cleared | 6/13/2024 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | DIANA RENTERIA |
| Construction near power lines | Cleared | 10/23/2024 | TINA MIRANDA |
Contact Information
| Architect | Mackler,, Deborah Ellen; Lic. No.: C35957 | 334 SYCAMORE ROAD SANTA MONICA, CA 90402 |
| Contractor | R & R Design And Builders Inc; Lic. No.: 1110570-B | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/2/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 5/22/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/15/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/15/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/17/2025 | Corrections Issued | DANIEL VERA |
| Underground Mechanical | 7/17/2025 | Partial Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 7/21/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 7/21/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 9/10/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Rough | 9/10/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 9/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 9/23/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 10/1/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 10/16/2025 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 12/1/2025 | Approved | DANIEL VERA |
| Sewer | 12/1/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 12/1/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | SEAN HAUPT |
| Green Building Rough | 12/8/2025 | Approved | SEAN HAUPT |
| Final | 12/10/2025 | Corrections Issued | SEAN HAUPT |
| Insulation | 12/10/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 12/19/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/5/2026 | Approved | DANIEL VERA |
| Shower Pan | 1/5/2026 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 3/10/2026 | Approved | EVAN COOPER |
| Final | 3/10/2026 | Corrections Issued | EVAN COOPER |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 3/10/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/10/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 3/10/2026 | Approved | EVAN COOPER |
| Final | 3/13/2026 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 3/13/2026 | Approved | RYAN SALAZAR |