629 1/2 N HARPER AVE 90048

Certificate Information: 629 1/2 N HARPER AVE 90048

Application / Permit
24016-30000-11020
Plan Check / Job No.
B24WL00694
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 4/24/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/5/2024 JASON JANGADA
Corrections Issued 4/7/2024 JASON JANGADA
Building Plans Picked Up 4/8/2024 APPLICANT
Plan Check Approved 4/24/2024 ZENA HADDIS
Issued 4/24/2024 APPLICANT
CofO in Progress 10/11/2024 JOSE MACIAS
Permit Finaled 10/25/2024 RUBEN SALAS
CofO Issued 10/25/2024 RUBEN SALAS
Permit Finaled 10/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/12/2024 ANTHONY TRAN
Sewer availability Cleared 4/12/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 4/15/2024 ANTHONY TRAN

Contact Information

Contractor Santa Fe Contractors Inc; Lic. No.: 951293-B 34385 ACTON CANYON RD      ACTON, CA 93510
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/30/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 5/20/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 5/20/2024 Corrections Issued AMIR NAZARIAN
Gas Test 5/20/2024 Approved AMIR NAZARIAN
Green Building Rough 5/20/2024 Not Ready for Inspection AMIR NAZARIAN
Insulation 5/20/2024 Corrections Issued AMIR NAZARIAN
METHANE-Rough 5/20/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 5/20/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 5/29/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 5/29/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 5/29/2024 Not Ready for Inspection AMIR NAZARIAN
METHANE-Final 5/29/2024 Approved AMIR NAZARIAN
METHANE-Rough 5/29/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 5/29/2024 Corrections Issued AMIR NAZARIAN
Deputy Drilled-In Anchors 6/11/2024 Conditional Approval AMIR NAZARIAN
ELECTRICAL-Rough 6/11/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 6/11/2024 Not Ready for Inspection AMIR NAZARIAN
Insulation 6/11/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 6/11/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 6/13/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 6/13/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 6/13/2024 Not Ready for Inspection AMIR NAZARIAN
HVAC-Rough 6/13/2024 Corrections Issued AMIR NAZARIAN
Insulation 6/13/2024 Partial Approval AMIR NAZARIAN
PLUMBING-Rough 6/13/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 6/24/2024 Approved AMIR NAZARIAN
Drywall Nailing 6/24/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 6/24/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 6/24/2024 Approved AMIR NAZARIAN
HVAC-Rough 6/24/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 6/24/2024 Approved AMIR NAZARIAN
Shower Pan 6/24/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 6/26/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 6/26/2024 Approved AMIR NAZARIAN
Shower Pan 6/26/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 7/9/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 7/9/2024 Approved AMIR NAZARIAN
ELECTRICAL-Final 9/3/2024 Approved JOSE MACIAS
Final 9/3/2024 Corrections Issued JOSE MACIAS
Green Building Final 9/3/2024 Approved JOSE MACIAS
HVAC-Final 9/3/2024 Approved JOSE MACIAS
PLUMBING-Final 9/3/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved JOSE MACIAS
Smoke Detectors 9/3/2024 Approved JOSE MACIAS
Final 9/24/2024 Conditional Approval JOSE MACIAS
Final 10/8/2024 OK to Issue CofO JOSE MACIAS